Monthly Operating Repts for Jan 1996 for Limerick Generating Station Units 1 & 2
ML20097D158
Person / Time
Site: Limerick  
Issue date: 01/31/1996
From: Gallagher M, Henricks D
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9602120210
Download: ML20097D158 (11)


Text

.

Umtrick C nsr tin 3 Statlin amm.

V PECO ENERGY

e J "; a' " ""'

Sanatoga. PA 19464-0920 T.S.6.9.1.6 February 8, 1996 Docket Nos. 50-352 50-353 License Nos. NPF-39 NPF-85 U. S. Nuclear Regulatory Commission Attn:

Document Control Desk Washington, DC 20555

Subject:

Limerick Generating Station Monthly Operating Report For Units 1 and 2 Enclosed are the monthly operating reports for Limerick Units 1 and 2 for the month of January 1996 forwarded pursuant to Technical Specification 6.9.1.6.

Very truly yours, Michael P. Gallagher Director - Site Engineering drh Enclosures cc:

T. T. Martin, Administrator, Region I, USNRC N. S. Perry, USNRC Senior Resident Inspector LGS W. C MacFarland, Vice President, LGS m

9602120210 960131 j

PDR ADOCK 05000352 j 'n gj R

PDR

,)

I t

\\

~

Docket No. 50-352 Attachment to Monthly Operating Report for January 1996 Limerick Generating Station Unit 1 January 1 through January 31,1996 1.

Narrative Summarv of Ooeratina Exoeriences Unit 1 began the month of January at a nominal 100% of rated thermal power (RTP).

On January 2,1996 at 2310 hours0.0267 days <br />0.642 hours <br />0.00382 weeks <br />8.78955e-4 months <br />, power was reduced to 84% RTP to remove the B Reactor Feedwater pump from service for planned maintenance. Power was increased to 90% RTP at 0310 hours0.00359 days <br />0.0861 hours <br />5.125661e-4 weeks <br />1.17955e-4 months <br /> on January 3,1996, following removing pump from service.

Power remained at 90% RTP for planned maintenance on the A Reactor Feedwater pump until power was reduced below 90% RTP due to end of cycle coastdown.

On January 28,1996 at 2315 hours0.0268 days <br />0.643 hours <br />0.00383 weeks <br />8.808575e-4 months <br />, power was reduced to 81% RTP to remove the C Condensate pump from service. Power was restored to 85% RTP on January 29 at 0015 hours1.736111e-4 days <br />0.00417 hours <br />2.480159e-5 weeks <br />5.7075e-6 months <br />.

I Unit 1 ended this operating period at 87% of RTP in end of cycle coastdown, ll.

Challenges to Main Steam Safety Relief Valves There were no challenges to the Main Steam Safety Relief Valves during the month of January.

i 1

)

AVERAGE DAILY POWER LEVEL' DOCKET NO. 50-352 UNIT LIMERICKUNIT1 DATE FEBRUARY 7,1996 COMPANY PECO ENERGY COMPANY DAVID R. HENRICKS REPORTS ENGINEER SITE ENGINEERING LIMERICK GENERATING STATION TELEPHONE (610)718-3772 MONTH JANUARY,1996 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-NET)

(MWE-NET) 1 1026 17 923 2

1022 18 919 3

922 19 898 4

926 20 915 5

926 21 911 6

923 22 911 7

926 23 910 8

918 24 899 9

910 25 903 10 922 26 878 11 921 27 889 12 921 28 891 13 917 29 881 14 920 30 890 1

15 914 31 874 16 931

OPERATING DATA REPORT DOCKET NO. 50 -3 %

DATE FEBr..JARY 7,1996 COMPLETED BY PECO ENERGY COMPANY DAVID R. HENRICKS REPORTS ENGINEER SITE ENGINEERING LIMERICK GENERATING STATION TELEPHONE (610) 711M772 OPERATING STATUS

1. UNIT NAME:

LIMERICK UNIT 1 NOTES: THERE WERE NO LOAD DROPS

2. REPORTING PERIOD:

JANUARY,_1996 GREATER THAN 20% THIS MONTH.

3. LICENSED THERMAL POWER (MWT):_ _ _ _ _ _ _ _

3293

4. NAMEPLATE RATING (GROSS MWE): _ _ _ _ _ _ _ _ _ _

1092

5. DESIGN ELECTRICAL RATING (NET MWE):

1055

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):

1092 l

7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):

1055

8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7 ) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVELTOWHICH RESTRICTED,IF ANY(NET MWE):

[

t

10. REASONS FOR RESTRICTIONS,IF ANY:

THIS MONTH YR-TO-DATE CUMULATIVE i

11. HOURS IN REPORTING PERIOD 744 744 87,648 j
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 72,967.7
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 O_0 0.0 16 HOURS GENERATOR ON-LINE 744.0 744.0 71,743.9
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 i
16. GROSS THERMAL ENERGY GENERATED (MWH) 2,182,142 2,182,142 222.323,037
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 710,200 710,200 72,344,680 l
18. NET ELECTRICAL ENERGY GENERATED (MWH) 682,007 k

682,007 89,473,479 1

+1 I

PAGE 1 OF 2 I

+

OPERATING DATA REPORT (CONTINUED)

DOCKET NO.

50 - 352 DATE FEBRUARY 7,1996 THIS MONTH YR-TO-DATE

' CUMULATIVE

[

t

19. UNIT SERVICE FACTOR 100.0 %

100.0 %

81.9 %

f

20. UNIT AVAILABILITY FACTOR 100.0 %

100.0 %

81.9 %

21. UNIT CAPACITY FACTOR (USING MDC NET) 86.9 %

86 9 %

75.1 %

l

22. UNIT CAPACITY FACTOR (USING DER NET) 86.9 %

86.9 %

75.1 %

23. UNIT FORCED OUTAGE RATE

.0 %

.0 %

4.3 % -~

24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

REFUELING OUTAGE SCHEDULED FOR 2!5/96 LASTING 20 DAYS.

j

25. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATIONS):

FORECAST ACHIEVED E

INITIAL CRITICALITY 12/19/84 12/22/84 INIT!AL ELECTRICITY mfd APRIL 85 04/13/85 COMMERCIAL OPERATION 1ST QTR 86 02K)1/86 L

b 6

4 5

?

l PAGE 2 OF 2 l

i UNIT SHUTDOWNS AND POWER REDUCTIONS l

DOCKET NO. 50-352 UNITNAME LIMERICKUNIT1 DATE FEBRUARY 7,1993 COMPLETED BY PECO ENERGY COMPANY l

DAVID R. HENRICKS I

REPORTS ENGINEER SITE ENGINEERING LIMERICK GENERATING STATION REPORT MONTH JANUARY,1996 TELEPHONE (610)718-3772 l

METHOD OF LICENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN EVENT CODE CODE ACTION TO NO.

DATE (1)

(HOURS)

(2)

REACTOR (3)

REPORT #

(4)

(5)

PREVENT RECURRENCE 92 960102 S

0.0 B

4 N/A CH PUMPXX REACTOR POWER WAS REDUCED TO 84% DUE TO PLANNED MAINTENANCE ON B REACTOR FEEDWATER PUMP.

93 960103 S

0.0 B

4 N/A CH PUMPXX REACTOR POWER REMAINED AT 90% DUE TO PLANNED MAINTENANCE ON A REACTOR FEEDWATER PUMP.

94 960128 S

00 B

4 N/A HH PUMPXX REACTOR POWER WAS REDUCED TO 81% DUE TO REMOVAL OF C CONDENSATE PUMP FROM SERVICE FOR MAINTENANCE.

TOTAL HOURS 0.0 (1)

(2)

(3)

(4)

F-FORCED REASON METHOD EXHIBIT G -INSTRUCTIONS S-SCHEDULED A -EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST 2-MANUAL SCRAM ENTRY SHEETS FOR UCENSEE C - REFUELING 3 - AUTOMATIC SCRAM EVENT REPORT (LER)

D - REGULATORY RESTRICTION 4-OTHER (EXPLAIN)

FILE (NUREG-0161)

E - OPERATOR TRAINING + LICENSE EXAMINATION F - ADMINISTRATIVE (5) l G - OPERATIONAL ERROR (EXPLAIN)

EXHIBIT I-SAME SOURCE H -OTHER (EXPLAIN)

Docket No. 50-353 Attachment to Monthly Operating Report for January 1996 Limerick Generating Station Unit 2 January 1 through January 31,1996 1.

Narrative Summarv of Ooeratina Exoeriences Unit 2 began the month of January at a nominal 100% of rated thermal power (RTP).

On January 5,1996 at 1641 hours0.019 days <br />0.456 hours <br />0.00271 weeks <br />6.244005e-4 months <br />, power was reduced to 70% RTP for hydraulic control unit maintenance. Power was restored to 100% RTP at 0558 hours0.00646 days <br />0.155 hours <br />9.22619e-4 weeks <br />2.12319e-4 months <br /> on January 9,1996.

On January 11,1996 at 1210 hours0.014 days <br />0.336 hours <br />0.002 weeks <br />4.60405e-4 months <br />, power was reduced to 85% RTP main turbine valve testing and a control rod pattern adjustment. Power was restored to 100% RTP at 1850 hours0.0214 days <br />0.514 hours <br />0.00306 weeks <br />7.03925e-4 months <br />.

On January 20,1996 at 0400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br />, power was reduced to 98% RTP for main turbine valve testing. Power was restored to 100% RTP at 0617 hours0.00714 days <br />0.171 hours <br />0.00102 weeks <br />2.347685e-4 months <br />.

On January 27,1996 at 0103 hours0.00119 days <br />0.0286 hours <br />1.703042e-4 weeks <br />3.91915e-5 months <br />, power was reduced to 98% RTP for main turbine valve testing. Power was restored to 100% RTP at 0225 hours0.0026 days <br />0.0625 hours <br />3.720238e-4 weeks <br />8.56125e-5 months <br />.

Unit 2 ended this operating period at 100% of RTP.

II.

Challenges to Main Steam Safety Relief Valves There were no challenges to the Main Steam Safety Relief Valves during the month of January.

i

AVERAGE DAILY POWER LEVEL 0,

DOCKET NO. 50-353 UNIT LIMERICKUNIT2 i

DATE FEBRUARY 7,1996 I

COMPANY PECO ENERGY COMPANY DAVID R. HENRICKS REPORTS ENGINEER SITE ENGINEERING UMERICK GENERATING STATION TELEPHONE (610)718-3772 MONTH JANUARY,1996 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-NET)

(MWE-NET) i 1

1137 17 1138 2

1137 18 1137 3

1141 19 1121 4

1137 20 1141 5

1075 21 1137 6

794 22 1141 7

797 23 1137 8

889 24 1133 y

9 1117 25 1137 10 1140 26 1137 11 1104 27 1129 12 1142 28 1136 l

13 1138 29 1140 14 1138 30 1140 15 1138 31 1132 16 1142

?

i OPERATING DATA REPORT 7

DOCKET NO. 50 -353 DATE FEBRUARY 7,1998 l

COMPLETED BY PECO ENERGY COMPANY 1

DAVID R. HENRICKS REPORTS ENGINEER SITE ENGINEERING I

LIMERICK GENERATING STATION t

TELEPHONE (610) 718-3772 i

i f

OPERATING STATUS f

1. UNIT NAME:

_.L_IME_R..I_CK_ _UN_IT 2.. '

I

2. REPORTING PERIOD:

JANUARY,1996 i

THAN 20% THIS MONTH TO

3. LICENSED THERMAL POWER (MWT) 3458 PERFORM HYDRAULIC CONTROL
4. NAMEPLATE RATING (GROSS MWE): __

1163 UNIT MAINTENANCE.

t

5. DESIGN ELECTRICAL RATING (NET MWE):

1115 t

i

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):

1155

7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):

1115

.j

8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7 ) SINCE LAST REPORT, GIVE REASONS:

l

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE):
10. REASONS FOR RESTRICTIONS,IF ANY:

i t

4 THIS MONTH YR-TO-DATE CUMULATIVE i.

11. HOURS IN REPORTING PERIOD 744 744 53,160
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 48,276.8

[

13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
14. HOURS GENERATOR ON-LINE 744.0 744.0 47,335.8

)

15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 i

t

16. GROSS THERMAL ENERGY GENERATED (MWH) 2,495,626 2,495,626 150,841,358 l
17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 845,800 845,800 49,923,680
18. NET ELECTRICAL ENERGY GENERATED (MWH) 820,843 820,843 48,124,474 i

f PAGE 1 OF 2 l

l

OPERATING DATA REPORT (CONTINUED)

I l

DOCKET NO.

50 - 353 DATE FEBRUARY 7,1968 THIS MONTH YR-TO-DATE CUMULATIVE

19. UNIT SERVICE FACTOR 100.0 %

100.0 %

89.0 %

20. UNIT AVAILABILITY FACTOR 100.0 %

100.0 %

89.0 %

21. UNIT CAPACITY FACTOR (USING MDC NET) 98.9 %

98.9 %

85.0 %

{

22. UNIT CAPACITY FACTOR (USING DER NET) 98.9 %

98.9 %

85.0 %

23. UNIT FORCED OUTAGE RATE

.0 %

.0 %

3.3 %

24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):

OUTAGE FOR ECU!PMENT RELIABILITY SCHEDULED FOR WEEK OF 5/12/96 TO LAST 1 WEEK.

?

25. IF SHUTDOWN AT THE END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL CPERATIONS):

FORECAST ACHIEVED INITIAL CRITICALITY 08/12,99 08/12/89 L

INITIAL ELECTRICITY 09/01/89 0901/89 COMMERCIAL OPERATION 02/01/90 01/00s90 i

r t

[

l

. PAGE 2 OF 2

- = -

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-353 UNITNAME UMERICKUNIT2 DATE FEBRUARY 7,1996 COMPLETED BY PECO ENERGY COMPANY DAVID R. HENRICKS REPORTS ENGINEER SITE ENGINEERING LIMERICK GENERATING STATION

=

REPORT MONTH JANUARY,1996 TELEPHONE (610)7184772 METHOD OF UCENSEE SYSTEM COMPONENT CAUSE AND CORRECTIVE TYPE DURATION REASON SHUTTING DOWN EVENT CODE CODE ACTION TO NO.

DATE (1)

(HOURS)

(2)

REACTOR (3)

REPORT #

(4)

(5)

PREVENT RECURRENCE r

89 960105 S

0.0 8

4 N/A RB CPDRVE REACTOR POWER WAS REDUCED TO 70% TO PERFORM HYDRAUUC CONTROL UNIT MAINTENANCE.

90 960111 S

0.0 B

4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 85% DUE TO MAIN TURBINE VALVE TESTING AND A CONTROL ROD PATTERN ADJUSTMENT.

91 960120 S

0.0 B

4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 98% DUE TO MAIN TURB!NE VALVE TESTING.

92 960127 S

0.0 B

4 N/A HA VALVEX REACTOR POWER WAS REDUCED TO 98% DUE TO I

MAIN TURBINE VALVE TESTING.

TOTAL HOURS 0.0 6

(1)

(2)

(3)

(4)

F-FORCED REASON METHOD EXHIBIT G-INSTRUCTIONS S-SCHEDULED A-EQUIPMENT FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B-MAINTENANCE OR TEST 2-MANUAL SCRAM ENTRY SHEETS FOR UCENSEE C-REFUEUNG 3 - AUTOMATIC SCRAM EVENT REPORT (LER)

D - REGULATORY RESTRICTION 4-OTHER (EXPLAIN)

FILE (NUREG-0161)

E - OPERATOR TRAINING + UCENSE EXAMINATION F - ADMINISTRATIVE (5)

G-OPERATIONAL ERROR (EXPLAIN)

EXHIBIT I-SAME SOURCE H - OTHER (EXPLAIN)

---..