ML20096H534

From kanterella
Jump to navigation Jump to search

Advises That All Actions Associated W/Generic Ltr 88-17 Completed.Shutdown Cooling Low Flow Alarm Instrumentation Installed During 1992 Refueling Outage
ML20096H534
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 05/21/1992
From: Gates W
OMAHA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-88-17, LIC-92-170R, TAC-M69744, NUDOCS 9205270279
Download: ML20096H534 (2)


Text

-

-.__--L_.__.

Omaha Public Power District 444 South 16th Street Mall Omaha, Nebraska 68102-2247 402/635-2000 May 21, 1992 LIC-92-170R U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station Pl-137 Washington, DC 20555

References:

1.

Docket No. 50-285 2.

Letter from OPPD (W. G. Gates) to NRC (Document Control Desk) dated April 12, 1990 (LIC-90-0284) 3.

Letter from NRC (A. Bourniai to OPPD (W. G. Gates) dated August 10, 1990 (TACf69744) dated September 4(,1991 (LIC-91-20lR)W. G. Gates) to NRC (Document Contr Letter from OPPD 4.

5.

Letter from NRC (D. L. Wigginton) to OPPD (W. G. Gates) dated December 5, 1691 6.

Letter from Gh 1 (W. G. Gates) to NRC (Document Control Desk)

Dated January 31, 1992 (LIC-92-018R)

Gentlemen:

~

SUBJECT:

Completim af Generic Letter (GL) 88-17 Actions In Reference 2,

Omaha Public Power District 0 PPD provided plans for installation of two instrumentation enhancements be(yond)GL 88-17 requirements, a Shutdown Cooling Low Flow Alarm, and Suction Pressure Indication at the Low Pressure Safety Injection (LPSI) and Containment Spray (CS) Pumps. Reference 3 requested that OPPD inform the NRC when the modifications were completed.

As noted in Reference 4,

OPPD revised the enhancement plans to cancel installation of the LPSI/CS Suction Pressure instrumentation. The NRC requested additional information in Reference 5; this was provided and discussed in a telephone conversation on February 6,1992 between OPPD and Messrs. S. D. Bloom and W. C. Lyon of the NRC.

The Shutdown Cooling Low Flow Alarm instrumentation was installed during the 1992 Refueling Outage. All actions associated with GL 88-17 for Fort Calhoun Station are therefore considered complete.

9205270279 920521 ADOCKOS00g5 PDR nay-pol

e

~

U. S. Nuclear Regulatory Commission LIC-92-170R Page 2 If you should have any questions, please contact me.

Sincerely iYNat4/

  1. 1/ W. G. Gates

~

Division Manager Nuclear Ooerations ej WGG/sel c: