Interim Deficiency Rept DER 83-57 Re Cracks in Control Element Assembly Shroud.Initially Reported on 830729. Requests Extension Until 840915 for Submittal of Final Rept to Allow for post-demonstration Test Insp Evaluation
ML20095H050
Person / Time
Site: Palo Verde  
Issue date: 08/13/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-30187-TDS, DER-83-57, NUDOCS 8408280302
Download: ML20095H050 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

1

)

s.

RECElVED URO Arizona Public Service Company IB AUG I7 PH 1: 00 REGIONVIAE August 13, 1984 ANPP-30187-TDS/TRB U. S. Nuclear Regulatory Commission 1

Region V Creekside Oaks Office Park 1450 Maris Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Time Extension For Report - DER 83-57 A 50.55(e) Potentially Reportable Deficiency Relating To Cracks In The Control Element Assembly Shroud.

File: 84-019-026; D.4.33.2 I

Reference:

(A) Telephone conversation between P. Johnson and R. Tucker on July 29, 1983 (B) ANPP-27598, dated August 19, 1983 (Interim Report)

(C) ANPP-28093, dated October 26, 1983 (Time Extension)

(D) ANPP-28654, dated January 20, 1984 (Interim Report)

(E) ANPP-29715, dated June 11, 1984 (Time Extension)

(F) Telephone conversation between P. Narbut and T. Bradish on August 14, 1984

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), Interim Reports were transmitted by Reference (B) and (D) and Time Extensions were requested by Reference (C) and (E). At that time, it was estimated that a Final Report would be available by August 15, 1984.

As discussed in Reference (F) the Post Demonstration Test Inspection is in process. The results of the inspection must be evaluated prior to submittal of the Final Report. APS expects this report to be completed prior to August 31, 1984, however, a time extenstion is requested until September 15, 1984.

8408280302 840813 PDR ADOCK 05000528 PDR S

'l*

ZEv7

m

['>

Mr. T. W. Bishop DER 83-57 Page Two There is no new information or change to the Interim Report at this time.

Very truly your

?.9. w W d n E. E. Van Brunt, Jr.

APS Vice President Nuclear Production ANPP Project Director EEVB/TRB/nj cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

D. B. Karner W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza D. E. Fowler T. D. Shriver C. N. Russo J. Vorees J. R. Bynum J. M. Allen J. A. Brand A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson L. E. Vorderbrueggen R. P. Zimmerman S. R. Frost J. Self M. Woods T. J. Bloom Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 l

Atlanta, GA 30339 l

. _. _ _ _ - _ _ ~. _

-