.r CP&L Carolina Power & Light Company SERIAL: NLS-84-360 AUG 16'1984 Director lof Nuclear Reactor Regulation
. Attention: ~ Mr.. D. B. Vassallo, Chief
. Operating Reactors Branch No. 2 Division of Licensing United States Nuclear Regulatory Commission
. Washington, DC 20555 BkUNSWICK STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-324/ LICENSE NO._ DPR-62
-STARTUP.DATE-
Dear Mr..Vassallo:
The' purpose'of this letter is to inform you that the currently scheduled startup date for' Brunswick Unit No. 2 (Brunswick-2) is ' September 16, 1984.
This date has been revised from the originally scheduled startup date of
' September 25, 1984.
' Carolina Power'& Light Company (CP&L)' currently has five Technical
~
Specification (TS)' amendment requests pending at the NRC which are required to be issued prior to Brunswick-2 startup.. Our' amendment request regarding Hydraulic Snubbers (84TSB02, submitted May 7,1984) was prenoticed on July 24, 1984. The remaining four requests; Reload 5 (84TSB15, ' submitted June 26, 1984), Suppression Pool' Temperature Monitoring System (84TSB29, submitted June 29, 1984), Hafnium Control Rod Assemblies (84TSB23, submitted June 26,.
1984),~ and Drywell Sump -Instrumentation / Administrative Corrections (84TSB05,
' submitted May'10, 1984) have not yet been prenoticed.- Since these requests were notLprenoticed in the July 1984 Federal Register, the next opportunity.
l
-for prenoticing is approximately August 22, 1984.- Based on an August 22, 1984 publication date, the 30-day public comment period would then expire on September 21, 1984 allowing issuance of the amendments on or after
-September 22, 1984. This schedule creates the potential for delaying startup of Brunswick-2 due to non-issuance of the required Technical Specifications.
Carolina Power & Light Company therefore requests that the possibility of j;
early issuance of these amendments be considered if progress on critical path l
work continues to support a September 16, 1984 startup date. NRC action on
-our extension request pursuant to environmental qualification of ' safety-
~
related electrical equipment,_ submitted on April 25,'1984, is also required prior to Brunswick-2 startup. In addition, CP&L is currently preparing a j
submittal regarding IGSCC inspections performed on Brunswick-2 during the This submittal will include a j ustification for
. current refueling outage.
scontinued operation for an additional fuel cycle. We anticipate completion of I-this submittal by August 10, 1984.
l' geggjM g
P 411 Fayettevilte Street
- P. O. Box 1551
- RWeigh, N C. 2N02
[
Mr. D. B. Vessello
- The NRC Proj ect Manager for Brunswick will be kept informed of the currently scheduled startup date on a daily basis. Should you have any questions concerning this matter, please contact Mr. John S. Dietrich at (919) 836-6154.
Yours very truly, S.
.mmerman Manager Nuclear Licensing Section MAT /ccc (442 MAT) cc:
Mr. D. O. Myers (NRC-BNP) 4 M r. J. P. O'Reilly (NRC-RII)
Mr. M. Grotenhuis (NRC) 1
-