Special Rept:On 951205,both electric-driven & diesel-driven Fire Pumps Placed in pull-to-lock Position to Accommodate Preventive Maint on Fire Water Jockey Pump.Caused by Erroneous Pump Starts.Returned Pumps to Svc
ML20095C195
Person / Time
Site: Cooper Entergy icon.png
Issue date: 12/08/1995
From: Herron J
NEBRASKA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLS950241, NUDOCS 9512110406
Download: ML20095C195 (3)


Text

.

COOPER NUCLEAR STATION F

P.O. BOX 98. BROWNVLLE, NEBRASKA 68321 m-ONE -,,

Nebraska Publ.ic Power D. trict is rAx -

~.

NLS950241 December 8, 1995 U.

S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C.

20555

Subject:

Special Report Pursuant to Technical Specification 3.15.C.2 Cooper Nuclear Station, NRC Docket 50-298, DPR-46 Gentlemen:

On December 5, 1995, both the electric-driven and diesel-driven fire pumps were placed in the pull-to-lock position to accommodate preventive maintenance on the fire water jockey pump.

The Fire Suppression Water (FSW) System was thereupon rendered inoperable for approximately 2 M hours. Cooper Nuclear Station (CNS)

Technical Specification 3.15.C.2 requires the submittal of a Special Report by the following working day whenever the FSW System is inoperable. The report is to discuss the cause of the inoperability, action taken, and plans and schedule for restoring the system to operable status.

Cause of the Inonerability Flow for the CNS FSW System is provided by one electric-driven pump (FP-P-E) and one diesel-driven pump (FP-P-D).

An additional non-Technical Specification electric pump (FP-P-C) is available as an installed backup. The Fire Water Pumps auto-start on low fire water header pressure. An electric jockey pump maintains the header pressurized to prevent inadvertent pump starts.

On December 5, 1995, at 1437 fire water pumps FP-P-E and FP-P-D were placed in the pull-to-lock position to prevent automatic system actuation while the jockey pump was removed f rom service for a routine oil change.

This is needed to prevent potential pump damage due to erroneous pump starts resulting frott, the gradual system pressure decay that is seen when the jockey pump is out of service.

This configuration left FP-P-D and FP-P-E available for manual initiation. The backup electric pump was available for providing alternate FSW System capability.

Action Taken The electric-driven and the diesel-driven Fire Water pumps were returned to service at 1715 that day following the completion of the preventive maintenance on the jockey pump. The NRC was informed of this event by a required 24-hour telephone notification at 2309 on December 6, 1995.

Ng#['

9512110406 951200 M r 'll PDR ADOCK 05000298 B

PDR

$ $ $ M S h0lW!$$N: M lTEUl W OO M $ $ $ N b N 0 b $bN 0 Y NS $ $

==

==

_ =.

~===============u===

~~

i

-j.

NLS950241

  • December 8, 1995

'Page 2 1

G

' Plans and' Schedule for Mestorina System to Ooerability

-As discussed in the. previous paragraph, the Fire Suppression Water System has

, been. restored to operability. Owing to the short period of system inoperability, j

.the. availability of the primary electric and' diesel-driven fire pumps.for manual actuation, and the availability of.the backup electric. fire pump, the safety significance lof this event was low.

t It is recognized.that both the verbal notificacion and this written follow-up

.Special Report did not meet the timeliness requirements of the CNS Technical Specifications.

An investigation is.L being conducted via the CNS Corrective Action Program in order to prevent recurrence.

Sincerely,--

.-- A.

. T. Herron lant Manager

/nr l

cct L. J.

Callan j

G. R. Horn i

J. H. Mueller R. G. Jones R. A. Sessoms i

K.' C. Walden f

N. E..Champlin INPO Records Center NRC Resident Inspector l

W. Turnbull l

CNS Training.

l

~CNS Quality Assurance t

\\

I i

i l

I

o, q.

l LIST OF NRC COMMITMENTS ATTACHMENT 3 O

L Correspondence No; NLS950241 j

The following table identifies those actions committed to by the District in this document.

Any.other actions discussed in the submittal represent intended or

-planned actions by the District. They are described to the NRC for the NRC's information and are not regulatory commitments.

Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.