Text
..
.. ~ -
4 4
t INDEX NUMBER RECTION OF PAGES Average Daily Unit Power Level.
1 Operating Data Report 2
Refueling Information.
1 Monthly operating Summary.
1 Summary of Changes, Tests, and Experimeants.
9 i
i l
l l
l 92031700/7 923313 PDR ADOCK 05000354 R
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-354 UNIT Hone Creek DATE 3/13/92 COMPLETED BY V. Za biel'g}gi_
TELEPHONE (609) 339-3506 MONTH February 1992 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 1.
1054 17.
JR51 2.
1055*
1e -
1031 3.
1056*
19.
1076 4.-
1951 20.
1047 5.
1058*
21.
1065
'6.
1059*
22.
1064 7,
1049 23.
1044 8.
1Q 3, 24.
1952 9.
1Q11 25.
1952 10. -
1063 26.
1911 11.
1062 27.
1058 12.
1052 28.
1052 13.
1067 29, 1064 14.
1058 30.
EfA 15.
1051 31.
ELA 16; 1040
-oDue to an error in recording the meter readings, the exact average daily
. power levels for February 2, 3,
5 and 6 are unknown.
.The listed averages for those.four days represent the average of the appropriate two-day total.
_4 4
\\
OPERATING DATA REPORT DOCKET NO.
50-354 UNIT Have Creek DATE 3/13/92 COMPLETED BY V.
Zabielski TELEPHONE (609) 339-3506 OPERATING-STATUS 1.
Reporting Period February 1992 Gross Hours in Report Period 121 3.
Currently Authorized Power Level (MWt) 3293 Max. Depend. Capacity 1031 Design Electrical Ratin(MWe-Net) g (MWe-Net) 1067.
3.
Power Level to which restricted (if any) (MWe-Net)
None 4.
Reasons for restriction (if any)
This Yr To tienth -
Dato cumulative 5.
No. of hours reactor was critical 696.0 1440.0 38.60111 6.
Reactor reserve shutdown hours 222 D22 222 7.
Hours generator on line 696.0 1440.0 38,014.6 8.
Unit reserve shutdown hours 222 Ozg Atg 9.
Gross thermal energy-generated 2,287,882 4,731,220 120,728,362 (MWH)
- 10. Gross electrical energy 766,880 12 505,540 39,338,034 generated (MWH)
- 11. Net electrical energy generated 734,682 1,519,306 38,170,855
- 12. Reactor service factor 100.0 100.0 84.7
- 13. Reactor availability factor 100.0 100.0 14 2 2
- 14. Unit service factor 100.0 100.0 83.5
- 15. Unit availability factor 100 0 100.0 83.5
- 16. Unit capacity factor (using MDC) 102.4 102.3 81.3
- 17. Unit capacity factor 96.9 98.9 78.5 (Using Design MWe)
- 18. Unit forced outage rate 0.0 0.0 122
- 19. Shutdowns scheduled over next 6 months (type, date, & duration):
Maintenance outage, 3/7/92, 10 days
- 20. If shutdown at_end of report period, estimated-date of start-up:
N/A 4
+
1 e
OPERATING DATA REPORT UNIT S'IUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-354 UNIT Hope Creek DATE
_J/13/92 COMPLETED BY V,
Zabielski TELEPHONE (609) 339-3506, MONTH Februrry 1992 METHOD OF SHUTTING DOWN THE TYPE REACTOR OR F= FORCED DURATION REASON REDUCING CORRECTIVE NO.
DATE S= SCHEDULED (HOURS)
(1)
POWER (2)
AC7 ION / COMMENTS None.
1 1
Summary l
- =- -
\\
REFUELING INFORMATION DOCKET NO.52-354 UNIT Hone Creek DATE 3/13/92 COMPLETED BY S.
Hollingsworth TELEPHONE (609) 339-1051 MONTH February 1992 1.
Refueling information has changed from last month:
Yes No X
2, Scheduled date for next refueling:
9/12/92
.3.
Schedultd date for restart following refueling:
1.1/11/92 4.
A.
Will Technical Specificatio" changes or other license amendments be required?
Yes No X
B.
Has tuc-reload fuel design been reviewed by the Station Operating. Review Committee?
Yes No X
If no, when is it scheduled?
R2t scheduled (on or prior to 7/24/92) 5.
Scheduled date(s) for submitting proposed licensing action:
ELA 6.
Important licensing considerations associated with refueling:
- Same fresh fuel as current cycle:.no new considerations 7.
Number of-Fuel Assemblies:
A.
Incore 764 B.
In Spent Fuel Storage (prior to refueling) 252 C.
In. Spent Fuel Storage (after refueling) 1008 8.
Present licensed spent fuel storage capacity:
4006 Future spent fuel storage capacity:-
4006 9..
Date of last refueling that can be discharged 11/4. 2010 to spent fuel pool assuruing the present (EOC16) licensed capaci0y:
(does not allow ter full-core offload)
1 i
HOPE CREEK GENERATING STATION MONTHLY OPERATING
SUMMARY
February 1992 Hope Creek entered the month of February at approximately 100%
power.
The unit operated for the entire the month without experiencing any shutdowns or any reportable power reductions.
On February 29, the plant completed its 294th day of continuous power operation.
d
<-