Amend 92 to License NPF-29,changing Time Limit from 2 H to 24 H for Operability Testing of Remaining Diesel Generators If Generator 13 Inoperable
ML20094J477
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 03/09/1992
From: Larkins J
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20094J481 List:
References
NUDOCS 9203130062
Download: ML20094J477 (4)


Text

.

pa rtou o

UNITED STATES g

[,

g NUCLEAR REGULATORY COMMISSION 5

't W ASHINGTON. D. C,20$55 sf" o

....*a ENTERGY OPERATIONS. INC.

SYSTEM ENERGY RESOURCES. INC.

SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION MISSISSIPP1 POWER AND LIGHJ COMPANY DOCKET NO. 50-416 GRAND Gulf NUCLEAR STATION. UNIT 1 AMENQMENT TO FACllllY OPERATING LICENSE Amendment No. 92 License No. NPF-29 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Entergy Operations, Inc. (the licensee) dated August 13, 1991, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this am'-iment can be conducted without endangering the health and safety or the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

9203130062 920309 PDR ADOCK 05000416 P

PDR

1 2.

Accordingly, the license is amended by changes to the Technical Specifications, as indicated in the attachment to this license amendment; and paragraph 2.C.(2) of Facility Operating License No. NPF-29 is hereby amended to read as follows:

(2) lechnical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through-Amendment No. 92, are hereby incorporated into this license.

Entergy Operations, Inc. shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3.

This license amendment is effective as of its dato of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION I LS y

John T. Larkins, Director Project Directorate IV-1 Division of Reactor Projects - lil/IV/V-Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issuance:

March 9, 1992

-.-- - =-..--- -

ATTACHMENT TO LICENSE AMENDMENT NO. 92 fAtlllTY OPERATING LICEtllE NO. NPF-29 DOCKET N0. 50-416 Replace the following page of the Appendix A Technical Specifications with the attached page. The revised page is identified by amendment number and contains a vertical line indicating the area of change.

REMOVE PAGli E SERT PAGES 3/4 8-2 3/4 8-2 i

I f

I

~

~

-,-c...~..=

n,,

9

LIMITING CONDITION FOR OPERATION (Continued)

ACTION (Continued) c.

With one offsite circuit and diesel generator 11 or 12 of the above required A.C. electrical power sources inoperable, cemonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within I hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.

Demonstrate the OPERABILITY of the remaining OPERABLE diesel generators, for one diesel generator at a time, by performing Surveillance Requirement 4.8.1.1.2.a.4* within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

Restore at leest one of the inoperable A.C. sources to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

d.

With either diesel generator 11 or 12 of the above required A.C.

electrical power sources inoperable, in addition to ACTION b or c, as applicable, verify within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> that all required systems, subsys-tems, trains, components and devices that depend on the remaining OPERABLE diesel generator 11 or 12 as a source of emergency power are also OPERABLE; otherwise, be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

With both of the above required offsite circuits inoperable, demon-e.

strate the OPERABILITY of the three required diesel generators, by performing Surveillance Requirement 4.8.1.1.2.a.4* for one diesel generator at e time within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> unless the diesel generators are t

l already operating.

Restore at least one of the above required off-l site circuits to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, l

f.

With diesel-generators 11 and 12 of the above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remain-ing A.C. sources by performing Surveillance Requirement 4.8.1.1.1.a within I hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.

Restore at least one of the inoperable diesel generators 11 or 12 to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and demonstrate the OPERABILITY of diesel generator 13 within the next 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> by performing Surveillance Re-quirement 4.8.1.1.2.a.4* or be in at least HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

g.

With diesel generator 13 of the above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the offsite A.C.

sources by performing Surveillance Requirement 4.8.1.1.1.a within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter.

Demonstrate the OPERABILITY of the remaining OPERABLE diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 for one diesel generator at a time within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Restore diesel generator 13 to OPERABLE status l

within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or declare the HPCS system inoperable and take the ACTION required by Specification 3.5.1.

  • Specification 4.8.1.1.2.a.4 must be performed for diesel generator 13 only when the HPCS system is OPERABLE.

GRAND GULF-UNIT 1 3/4 8-2 Amendment No. 20, 92