ML20094G693

From kanterella
Jump to navigation Jump to search
Forwards Operational Readiness Review Plan for Resumption of Irts Operations,Hlw Treatment Phase II - Sludge Wash. Advises of 920309 Board Meeting & Overview & Summary of Results Will Be Discussed on 920319
ML20094G693
Person / Time
Site: West Valley Demonstration Project
Issue date: 02/25/1992
From: Rowland T
ENERGY, DEPT. OF, IDAHO OPERATIONS OFFICE
To: Gary Comfort
NRC
Shared Package
ML20094G697 List:
References
REF-PROJ-M-32 NUDOCS 9203030255
Download: ML20094G693 (1)


Text

.. - - - _ - - -

l

/ -3a k Department of Energy [p((,

?# < Idaho Operations Office West Valley Project Office g

pg'- P.O. Box 191 West Valley, NY 14171 l

February 25, 1992 Ar Mr. G. C. Comfort U.S. Nt2 clear Regulatory Commission Headquarters Washington D.C. 20555

SUBJECT:

Operational Readiness Review of West Valley High-Level Waste Sludge Wash Phase II IRTS Operations

Dear Sir:

Enclosed is a copy of the Operational Readiness Review (ORR) Plan for resumption of IRTS Operations for Sludge Wash. In accordance with our earlier discussions this letter is an invitation for you or your representatives to participate in the ORR activities as NRC

" observers." I have appointed an ORR Board with Steve Ketola as Chairman. We have two members from the Idaho operations staff supporting the review, and two members from NYSERDA. We will be following the WVNS schedule (attached to the plan) of presentations throughout the month of February and expect to have a week long Board meeting beginning March 9, 1992.

I have invited several DOE observers to attend meetings, receive documents, etc. Appendix A of the plan lists the board members and some observers, others may visit us as time permits. I have designated March 19, 1992, for a comprehensive overview and summary of the results of the readiness review preparations undertaken for our Phase II activities. I would encourage you to join us for this meeting since it would be the best time for you to see the total

" picture" of Phase II operations and readiness. Of course you are welcome to attend any of the interim discussions / meetings shown on the schedules if you are interested.

Please contact me on FTS 473-4312 or Steve Ketola of my staff on FTS 473-4314 with any questions.

Sincerol ,

MM T T. J; Rowland, Director West Valley Project Office

Enclosure:

ORR Plan WSK:012:92 - 1192:91:01 WSK/sl . - ~,

c- o n . g.-

400UJJ [2 l i

9203030255 92o223 PDR PROJ M-32 PDR

_ - - - -_ _ _ _ _ _ _