Forwards Application to Amend License DPR-59,changing Tech Specs Re NUREG-0737,Item II.K.3.18, Mod of Automatic Depressurization Sys Logic - Feasibility for Increased Diversity for Some Event Sequences
ML20093N389
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 07/25/1984
From: Bayne J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Vassallo D
Office of Nuclear Reactor Regulation
Shared Package
ML20093N390 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.18, TASK-TM JPN-84-50, NUDOCS 8408010319
Download: ML20093N389 (2)


Text

r

,m-123 Main Stree+

White Fiains. New York 10601 o'

314 681.6200 b

cut-V e President

& Authority

-o-""

July 25, 1984 w.

JPN-84-50 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Mr. Domenic B. Vassallo, Chief Operating Reactors Branch No. 2 Division of Licensing

Subject:

James A.

FitzParrick Nuclear Power Plant Docket No. 50-333 Proposed Change to the Technical Specifications Related to Automatic Depressurization System (ADS)

Logic Modification, NUREG-0737 Item II.K.3.18

References:

1.

NRC letter, D. G. Eisenhut to All Licensees, dated September 5, 1980 regarding Preliminary Clarification of TMI Action Plan Requirements.

2.

PASNY letter, J. P. Bayne to D.

B. Vassallo, dated March 31, 1983 (JPN-83-29).

3.

NRC letter, D.

B. Vassallo to J.

P.

Bayne, dated June 3, 1983 regarding same subject.

4.

NRC letter, D.

B. Vassallo to J. P. Bayne, dated June 5, 1984 regarding same subject.

5.

NYPA letter, J. P. Bayne to D.

B. Vassallo, dated July 25, 1984 (JPN-83-70) regarding same subject.

6.

BWR Owners' Croup letter, T. J.

Dente to a.

G.

Eisenhut, dated October 28, 1984 (BWROG-8260).

Dear Sir:

Enclosed for filing are three (3 ) signed originals and nineteen (19) copies of a document entitled, " Application for Amendment to Operating License," together with forty (40) copies of Attachment I and II thereto, comprising a statement of the proposed change to the Technical Specifications and the associated Safety Evaluction, l

p (0

04b t o,

u>1lPIL i

ys.

W Ilh 8408010319 840725

{

4t PDR ADOCK 05000333 P

PDR

The changes proposed in the attached application are the direct result of plant modifications to implement the requirements of Item II.K.3.18 of NUREG-0737 (Reference 1).

Via Reference 6, the BWR Owners' Group (BWROG) sent to the NRC a study of alternatives to the present ADS actuation logic.

This report also identified modifications that would eliminate the need for manual ADS actuation during postulated accident conditions to ensure core coverage.

In Reference 2 the Authority formally endorsed this report.

Th6 NRC evaluated the Owners' Group report and concluded that two of the seven alternatives are acceptable (Reference 3).

The Authority subsequently decided to implement the first of these two acceptable alternatives elimination of the high drywell pressure permissive and the addition of a manual inhibit switch (Reference 5).

The NRC closed the issue, finding the proposed modifications acceptable (Reference 4) based upon the Authority's commitment to complete the modification by April 30, 1985.

The Authority plans to complete these modifications during the upcoming Fall 1984 outage - well in advance of the April 1985 commitment date.

Since your approval of these changes is required prior to startup from this outage, your prompt attention to this amendment application is requested.

In accordance with 10 CFR 50.91, a copy of this application, with attachments, is being provided to the designated New York State official.

Enclosed is a check for $150.00 as the application fee per 10 CFR 170.12 (c), which the Authority pays under protest pending a final determination of the legality of the fee schedule.

Very truly yours, bJW P.

Bayne Executive Vice President Nuclear Generation cc:

Office of the Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, New York 13093 Mr. J.

D.

Dunkleberger Division of Policy An& lysis and Planning New York Sate Energy Office Agency Building 2, Empire State Plaza Albany, New York 12223