ML20093F747

From kanterella
Jump to navigation Jump to search
Forwards Third Status Rept of Core Spray Sys Idvp for 820616-840630.Related Correspondence
ML20093F747
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 07/02/1984
From: Carpenter F
TORREY PINES TECHNOLOGY
To: Boyer V
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
References
OL, NUDOCS 8407230113
Download: ML20093F747 (7)


Text

%

-_ l ret:AT trE ' . ;. 4D&Ci I l

TORREY PINES TECHNOLOGY

/,[ \\ f

[; Po. Dos 85600 ,

C Mn Dego, Cahtornia 92138 Tew;, hone: (6t9) 455 2654 Por A Dwoon ot GA Technologies Inc. O&c. E0

>c 12 gg, -.

TFT:013: C:84 M" cr '

July 2,1984 .

' si,;,

Philade1#11a Electric Company 2301 Market Street 325-1 Fhiladel;hia, PA 19101 ,

gg; , . -- ,

gg g Attention: V. 3. Boycr, Sr. Vice President Nuclear Pc[eN Gentlemen:

The enclosed status report is the third of six scheduled Station Unit 1 forCore theSpray Independent Syntem.

Design Revios of the Limerick Generatin6 16, 1982 to June 30, 1984. A mangwer

'Ihis report covers the period June activity surmary graph illustrates the planned projected vs. actual effort to meet the IDVP milestones in the Program Plan.

A copy of this report is being sent directly to the representative of the U.S.

Nuclear Regulatory Commission.

Please call me if you have any questions regarding the contents of this report.

Sincerely, F. D. Carpenter FDC/dn Project Manager Enc 1.

cc: PECo: R. A. Mulford N2-1 E. C. Kistner J. Moskiwitz L. B. Pyrih G. J. Beck Bechte1: S. J. Ployhar USNRC: J. M. Milhoan, Chief Licensing Section Quality Assurance Branch, Office of Inspection & Enforcement U.S. Nuclear Regulatory Commission EWS 305A Washington, DC 20555 ,

8407230113 840702 '

PDR ADOCK 05000352 R PDR

cc: Judge Lawrence Brenner (w/ enclosure)

Judge Peter A. Morris (w/ enclosure)

Judge Richard F. Cole (w/ enclosure)

Troy B. Conner, Jr., Esq. (w/ enclosure)

Arun P. liodgdon, Esq. (w/ enclosure)

Mr. Frank R. Romano . (w/ enclosure)

Mr. Robert L. Anthony (w/ enclosure)

Maureen Mulligan (w/ enclosure)

Charles W. Elliott, Esq. (w/ enclosure)

Zori G. Ferkin, Esq. (w/ enclosure)

Mr. Thomas Gerusky (w/ enclosure)

Director, Penna. Emergency (w/ enclosure) tenagement Agency Angus Inve, Esq. (w/ enclosure)

David Wersan, Esq. (w/ enclosure)

Robert J. Sugarman, Esq. (w/ enclosure)

Martha W. Bush, Esq. '

(w/ enclosure)

Spence W. Perry, Esq. (w/ enclosure)

Jay M. Gutierrez, Esq. (w/ enclosure)

Atomic Safety & Licensing Appeal Board (w/ enclosure)

Atomic Safety & Licensing Board Panel (w/ enclosure)

Docket & Service Section (w/ enclosure - 3 copiec))

James Wiggins (w/ enclosure)

Timothy R. S. Cdmpbell (w/ enclosure) s I

e M

(

INDEPENDENT DESIGN REVIEW OF LIERICK GBIERATING STATION #1 CORE SPRAY SYSTEM

.Bi-Monthly Status Report #3 Period Ending June 30, 1984 Introduction Eis report docu-his is the third of six planned bi-monthly status reports.

ments information concerning the independent design review of Limerick's Core Spray - System.

Be work performed covers the period June 16, 1984 to June 30, 1984.

N Sumary Be design procedure, design doctmient implmentation, and technical reviews are progressing and have increased in intensity with the addition of five temporary reviewers. A site visit was made to GE for Task A work to define this During the structure visit the of GE design control procedures applicable to the CSS.

implementation of procedures for design control audits was reviewed as rcquired in Task B.

A good portion of the Task C technical review for GE involved features must be conducted at the GE facility since they will not tronanit calculations, vendor reports, or electrical instrunentation drawings. Bis is further complicated by having to review calculations on microfilm or waiting for microfilm reproduc-tion.

De walkdown to determine the physical installation of selected portions of the CSS is complete with the internal summary report issued June 22, 1984.

To date, six potential findings have been initiated and are being processed as required by TPr's procedure. All have been sent to the original design-organi-zation, Bechtel, for their review and response.

Specific detailed status on each task follows:

T = =le A DeMan Procedure Reviqw Al Complete - Procedures 2524-PD-1 & 7 issued.

Bechtel and GE design procedure A2 - PEco design procedure review is complete.

review continues. Wo TFT staff

~

reviewers visited GE the week of June 25, 1984 to establish the detailed structure of the design control procedures applicable to the CSS.

'A3 Bechtel and some GE procedures were transitted to TPI the week of June 18, 1984 The staff reviewers, mentioned in A2, returned with additional procedures identified during their visit. ,

A4 Bechtel design procedures are being reviewed under AS.

x-

. Bechtel and GE procedure AS PEco procedure conformance to PSAR is complete.

conformance is nearin6 completion.

l A6 Early procedure revisions are being obtained fra Bechtel and GE.

A7 No activity to date.

Task B DesiFn Procedure Imolementation Review B1 Complete - Procedure 2524-PD-2 issued.

B2 Docment ~1ists are being developed for Bechtel and GE and for specific design docments subjected to PECo review.

B3 Activity being coordinated with Gil.

Bil Review of PECo's design control audit activity was completed. Implementa-tion of GE procedures for design control audits was reviewed during the visit to GE.

B5 No activity to date.

_ Task C Technical Review C1 Complete - Procedure 2524-PD-3 issued.

C2 Completion of the design chain will be delayed until all vendors have been identified. De receipt of design docments continues as noted in C4 belcw.

C4 he Bechtel design docments that were initially requested but on hold pending execution of the nondisclosure agrement have been received during this report period. Additional docments identified as the review progresses are being obtained.

De visit to GE's facilities to screen and obtain doctuents required frm GE to initiate the review of the NSSS supplied components in the core Many of the doctments were available and spray system was productive.

were hand carried to San Diego..

However, all. calculations, vendor reports,Sme and of electrical instrmentation the analyses which are drawings will have to be reviewed at GE.

on microfilm will require one to four weeks to reproduce before they are available for review.

the contairment penetration De technical review of ASME Class 1 piping,Se review of Class 2 piping, pipe and selected instruments continues. the reactor vessel supports, the core spray pmp and ptmp anchorage, nozzle, core spray piping inside the containment, core spray sparger, and several valves in the core spray line were initiated.

O

- Many of the GE analyses for Limerick components refer to similar Verifica- analyses previously tion of similarity, performed for comparable components in other plants. cou docments discussed above, may impact the scheduled completion date for Task C. Expected doctmenation difficulties will be monitored by feature to eliminate or minimize any schedule impact.

C5 No activity to date.

C6 No activity to date.

Task D Physical Verification D1 Complete - Procedure 2524 issued.

D2 Complete - mano 2524-ENG:03:AS:84.

15, 1984. Four potential D3 Complete - the walkdown was colnpleted on June finding reports were initiated. Copies were sent to Bechtel for valication confirmation. Items potentially impacted by a HELB of the core spray line for loop A were identified for use in the design review.

D4 Complete - mano 2524:ENG:07:CFD:84 was issued on June 22, 1984.

Task E Potential Findings El - E2 Complete For this period, one potential finding was initiated within Task C and four were initiated with Task D. 'Ihe PFRs concern the containment Processing penetra- of these tion, piping, pipe supports, and whip restraints.

potential findings was initiated, i Task F Administrative and Reoorting Five additional personnel have been temporarily assigned to assist in the independent design review effort. 'IWo were assigned to assist in the Task

'Ihese additional persons A and B review and three in the Task C review. A swmary of have completed their project independence questionnaires.

their technical or design related capabilities and/or experiences will be transnitted under a separate letter. ,.

9 9

6

.)

i N

p - - - . - . . - - . W -----yw--y-g wpw,,-.g -.----9, -,yygy -. - -

y,g. .--,.w. -

---.yn-. e-y,-p---n- m.+n .-- - --- - --

Juns 30,1984 TABLE I CORE SPRAY SYSTEM INDEPENDENT DESIGN REVIEW TASK / MILESTONE STA'11)S Actual Document Milestone Subiect Ech 5/30 5/24 2524-FD-1 & 7 Al Procedure / Checklist

  • Procedure Structure 6/ 15 A2 6/ 15
  • A3 Access DesiEn Procedures A4 Bechtel Review 7/05 7/05 2524-QA-01 AS PEco/GE Review A6 Time-period Procedures 7/10 A7 Task Sunnary 7/24 5/30 5/24 2524-PD-2 B1 Procedure / Checklist
  • B2 Docunent Selection 6/15 B3 Docunent Location 7/01 B4 Docunent Review 7/27 B5 Task Sunmary 8/10 5/30 5/30 2524-PD-3 C1 Procedure / Criteria
  • C2 Design Chain 6/08 Feature Selection Cont 2524:ENG:02:AS:84 C3 C4 Design Review 8/10 C5 Independent Analysis 7/27 C6 Task Sunmary 8/17 Walkdown Procedure 5/30 5/31 2524-PD-4 D1 Item Selection 6/04 5/29 2524:ENG:03:AS:84 '

D2 D3 Complete Walkdown 6/27 6/15 '

D4 Task Sumnary 8/10 6/22 2524:ENG:07:CFD:84 Establish Committee 5/30 5/18 Proj. Directive #3 El 2524-PD-5 E2 Define Criteria 5/30 5/25 Procedure 5/30 5/30 2524-PD-5 E3 E4 Processing PFRs cont Management / cost cont - Project Directive #1 F1 Protocol Procedure 6/01 6/01 2524-PW6 F2 Status Report #1 6/1 5/31 TPr:005:FDC:84 F3 TFT:012:FDC:84 Status Report #2 ' 6/ 15 6/ 15 Status Report #3 7/1 7/2 TPr:018:FDC:84 Status Report #4 7/15 Status Report #5 8/1 Status Report #6 8/15 F4 Information Compilation 8/15 F5 Final Report Draf t 8/24 F6 Final Report-Issue 8/31

  • Extended - see status report comments

a i

$ h 6 e-0 0 0 0 0 0 0 0 0 0 0 5 4 3 2 1 0 9 8 7 6 1

~  %

' . ?. s 1 0 3 1

- 9 7 4 2

l 4 0 2 7

- 8 0 4 2

l T 7 0 S 1 3 U - 8 G 3 4 U 1 A l 0 0 1 3

- 6 6 4 0

. 4 0 0 9

- 2 0 4 3 '

'0 7

2 3

- 9 4 3 3 2 2 5 2

4 0 2 9 T

- 4 C 6 3 E 1 J Y O L 0 R U 3 9 P J 1 0

- 3 YW 9 R E 0 A I

I

$' 0 D VE 0 9  ?

- 6 U R 2 2 S 0 N l I. l1 jl Y G

'9, 0 T I 2 2 I S

- 3 V E 5

2 I D 2 - T C T 4 0 A N 2 2 E

- 9 D 8 1 N E 1 E N j P U 5 , 0 E J 1 0 D N

1

- 's 5 1 I 1 /

o l

8 / 0 9 C 0_ - 0 61 E

- 1 P 4 1 1 0

?.'

1 0

', 0 8

8 3

8 / 6 8 2

l 5

2 1-

/ 0 5

3 5 2

5 Y 2 A l8 M 1 Y 0 7

- 3 5 1 3 l

4 1 ,

1 1 0 0

- 1 0 7 2 0 l 0 0 0 0

0 0

0 0

0 0 0 d

0 0 0 0 0 4 3 2 1 e l 5 t a c u Egh e t j c o A r

P

%