ML20092P097

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in IE Insp Repts 50-321/84-07 & 50-366/84-07.Corrective Actions:Mgt Overview Committee Established to Review safety-related Maint Requests
ML20092P097
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/13/1984
From: Gucwa L
GEORGIA POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20092P091 List:
References
NED-84-193, NUDOCS 8407050405
Download: ML20092P097 (5)


Text

,-

_ _. -. ~ _.

' ' Georgia' Power Corrpany:

333 Piedmont Avenue Atlanta, Georgia 30308 O

Telephone 404 5266526 Mailing Address:

Post Othee Box 4545 -

Atfanta, Georgia 30302 17Geggaggwer m

L T.Gucwa the southern e:octrc system Manager Nuclear Engineenng and Chief Nuclear Eng neer NED-84-193 April 13,1984 U. S. Nuclear Regulatory Coussission -

REFERENCE:

' Office of Inspection and Enfortement RII: RCL Region -II - Suite 2900 _

50-321/50-366 101 Marietta Street, NN I6E Inspection Atlanta, Georgia 30303 Report 84-07 A1TENTION: Mr. James P. O'Reilly GENTLEMEN:

Georgia Power Company provides the following response _ to violations identified during an inspection conducted on January 21 - February 20, 1984, ard : reported by your letter dated March 14, 1984.

VIOLATION 1:

10'CFR 50, Appendix B, Criterion X, as. implemented by Section D.9 of the Hatch Unit 1 Final Safety Analysis Report (FSAR) and Section A.33 of the' Hatch Unit 2 FSAR, requires the licensee to comply with -ANSI N18.7-1976.

Section 5.2.7 of ANSI N18.7-1976 specifles that maintenance and modifications which may affect. functioning of safety-related ~ systems be performed in a manner to ensure quality at least equivalent _to that saecified in original ~ design bases and requirements.

It also specifies

- ttat a suitable level of' confidence in systems on which maintenance or modifications have been-performed shall be attained by appropriate inspection.

Contrary to. the above,_ on February 16,.1984, the NRC inspector identified a system not restored to original design requirements in'that the thermalJ insulation and electrical heat. tracing -on approximately a l'

- three foot section of piping downstream of the Unit 1, Division.,1, Plant Service Water strainer A backwash -valve, P41-F313A was ' not properly restored.

11his'is a Severity' Level IV violation (Supplement 'I) for Unit 1 only.

0407050405 840620 PDR ADOCK 05000321 G

PDR o

.~.

L GeorgiaPowerA I

U. S. Nuclear Regulatory Commission Office of Inspection and Enfortement Region II - Suite 2900 April 13,1984 Page Two 1

RESPONSE 'IU VIOLATION 1:

Admission or Denial of Alleged Violation: The violation occurred.

Reason - for the Violation:

The safety-related Maintenance Request (m) did not adequately describe the work to be perfomed.

2 1-83-5911 which controlled the work to be performed did not address restoration of 4

the thermal insulation and electrical heat tracing following repair of the pipe. 'Ihe E was completed on December 5, 1983.

Corrective Steps Which Have Been Taken and the Results Achieved:

On January 30, 1984, a Management Overview Committee was established to review safety-related Ms for proper work instructions and adequacy of the functional test requirements prior to. work being perfomed.

The insulation and heat tracing were properly replaced and the system was restored to original design requirements on February 23, 1984.

Corrective Steps Which Will-Be Taken to Avoid Future Violations:

The entire maintenance work order process is being-changed to require - that MRs pass through a work control center for review and. processing.

This group reviews MRs to ensure that they contain sufficient information for work to be performed properly.

Until-this_-new process is fully functional so as to ensure adequate m review and processing, the Management Overview Conmiittee will be responsible for reviewing safety-related MRs. -

Date When Full Compliance Was Achieved: Full compliance was achieved on Febntary 23, 1984, when the system was restored to original ' design requirements..

VIOLATION 2:

Technical Specification 6.8.1 requires that written procedures be implemented.

Contrary to 'the

above, procedure HNP-2-1500, Primary Containment-Atmospheric Control Systems, was not properly implemented :due to a

procedure iinadequacies in that, between July 2, 1983 and February 3, 1984, during periods of Unit 2 ' containment inerting evolutions, no

~ procedural provision. existed to prevent ' nitrogen being admitted to the-torus:at temperatures below the.specified band of:100-250F.

This is a Severity Level IV violation (Supplerent.I) for Unit 2 only.

7oons:

~

~

Georgia Power d U..S. Nuclear. Regulatory Commission k

Office of Inspection and Enforcement

. Region II - Suite 2900

- April 13,1984 ~

Page Three -

RESPONSE TO VIOLATION 2:

Admission or Denial of Alleged Violation: The violation occurred.

Reason for the Violation:

Plant Hatch procedure HNP-2-1500, Primary Containment Atmosphere Control Systems, did not adequately ensure proper operation of the nitrogen inerting. system.

This procedural inadequacy allowed the nitrogen temperature at the vaporizer controller (T48-B001) to drop, during containment inerting, below the specified band of 100-2500F.

The procedure specifically cautioned against operation of the vaporizer below 1000F., but did not specify actions to be taken if the temperature did fall below the specified band.

It is to be noted

. that HNP-2-1500 addresses vaporizer controller temperature, and not the i.

. temperature of the nitrogen downstream of the vaporizer..

Corrective Steps Which Have Been Taken and the Results Achieved: Unit 2 was shutdown at the time of discovery of the procedure deficiehcy and is still shutdown until approximately July,1984. Therefore, the immediate corrective steps taken were focused on Unit I which was operating at the time.

Standing Order 84-07 was issued February 6, 1984, to monitor torus temperature while inerting containment.

Plant Hatch procedure HNP-1-1500, Primary Containment Atmospheric Control Systems, was revised and approved for use on March 2,1984.

Corrective Steps Which Will Be Taken to Avoid Future Violations:

Plant Hatch procedure HNP-2-1500 is currently in the revision process and will

-be revised prior to startup - from the current outage and, more importantly, prior to the reintroduction of nitrogen to the torus.

Date When Full Compliance Was Achieved:

Full compliance will be l

achieved prior to startup when HNP-2-1500 will be revised and re-issued to prevent nitrogen from being admitted to the torus :at low temperatures.

VIOLATION 3:

. Technical Specification 6.8.1 requires that written procedures 'be implemented Contrary to the above, on February 15,-

1984, the NRC inspector lE discovered that:

l l

-,n

-.-~

j' l

L

. Georgia Power A U..S. Nuclear Regulatory Consiission Office of Inspection and Enforcement 4

' Region.II - Suite 2900 April 13,1984.

Page Four VIOLATION 3 (Continued):

a.

Pmcedure HNP-809, Section F.1.b, Plant Modifications Approval and Implementation, was not properly implemented in that Design Change Request 83-28 was closed out without the appropriate changes being made to Unit 1 drawing H-11304, Fire Pmtection P6ID, as required by As-Built Notice 83-238.

b.

Procedure HNP-812, Section E.4, As-Built Notice was inadequate in that the procedure only requires. verification that the appropriate As-Built Notice number appear in the drawing 1'

i revi_sion block.

No requirement exists for verifying that the specified change had accurately been made to the drawing, as described in 1 above.

i This ~is a Severity Level V violation (Supplement I) for Unit 1 only.

i

RESPONSE

Admission or Denial of Alleged Violation:

A violation of NRC j

mquirements occurred.

However, we do not agree with the violation as wri tten, in that the specific procedures cited.in the Notice of i

j Violation were adequate and not violated.

Procedure. HNP-809, Plant M>difications Apprrsval and Implementation, requires that the As-Built Notices (ABN) fom be filled in and sent to the Architect / Engineer (A/E)-

prior to Design Change Request (DCR) closeout.

ABN 83-238 was filled'in and sent to the A/E before the closecut of DCR 83-28.

As stated in the Notice of Violation, drawing H-11304' indicated that ABN 83-238 had been incorporated into the: drawing. ' HNP-812 requires verification that the

' appropriate As-Built Notice number ' appear in the drawing revision block.

It was not,. and is not, our intent that JHNP-812 address the ergineerimg process of incorporation of the ABN into a drawing.

Rather, this function is prescribed by procedures -controlling our A/E's implementation of i the ABN ' process which ensure / that the ABN has been

[

incorporated properly.

In this case the A/E, Southern Company Services, L

failed -to follow their procedures' governing this action. We, therefore, conclude that a. violation of Technical-Specification 6.8.1 did.not occur regarding this action..The. following response addresses the violation of NRC requirements.

(.

I 4

i toons

~

GeorgiaPower d U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region II - Suite 2900 p

April 13,1984 Page Five RESPONSE ID VIOLATION 3 (Continued)

Reason for the Violation:

A/E Design Engineering personnel failed to follow their existing procedures.

Previous annual audits by Georgia Power Company and Southern Company Services corporate Quality A.csurance I

departments have found the A/E's controls over ABN incorporation to be satisfactory.

This includes review of the adequacy of procedures for checking of drawings prior to issuance.

Based on the results of those audits,'we conclude that this is an isolated incident and is not indicative of a programmatic deficiency.

Corrective Steps Which Have Been Taken and the Results Achieved:

Drawing H-11304, Fire Protection P61D, was revised to incorporate AEN 83-238 correctly. This was completed on February 21, 1984.

Corrective Steps Which Will Be Taken to Avoid Future Violations:

Georgia Pbwer Company and Southern Company Services corporate Quality Assurance departments will-continue to aud_it the area of ABN~

incorporation -during their annual audits.

Special emphasis of this area will be included in the next scheduled audit.

Date When Full Compliance Was Achieved: Full compliance was achieved on February 21, 1984, when As-Built Notice 83-238 was incorporated properly into drawing H-11304.

If you have any questions regarding this response or require further information regarding our actions in'this matter, please contact this office.

Very truly yours, l

gf @ A L. T. Gucwa WB xc:

J. T. Beckham, Jr.

H. C. Nix, Jr.

l Senior Resident Inspector I

l 1,.

._ ~ ;

-,_ _ _