Forwards Updated Status List of Scheduled Completion Dates for NRC Emergency Plan Appraisal App a Open Items
ML20092M523
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/25/1984
From: Kuykendall J
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
TNRC-8415, NUDOCS 8407020284
Download: ML20092M523 (5)


Text

.

TNRC-8415 TEXAS UTILITIES GENERATING COMPANY F. o. sox 2300. cLEN ROSE, TEXAS 76043 J. C. KUYKENDALL May 25, 1984 MANAGER NUCLEAR OPERATmNS f

r f - Y$ h*N gro - pys/&4'-/7 2@20W2 Y

)!

MAY 2 S l00,1 Mr. Eric Johnson Region IV j

U. S. Nuclear Regulatory Commission 611 Ryan-Plaza Drive, Suite 1000 Arlington, Texas 76011

Subject:

Scheduled Completion Dates for NRC Emergency Plan Appraisal Appendix A Items

Dear Mr. Johnson:

~

i Attached is an updated (May 25, 1984) status list of Appendix A Open Items.

Some items have been completed and we would like to extend the dates of a

some others.

If you have any questions or require additional information, please contact Mr. Jay:Laughlin at (817) 897-4856, extension 3756.

Sincerely,y

/

l2%

JCKg1m1

~

Attachment-4 9

~

/po<

8407020284 840525 1

e PDR ADOCK 05000445 F

PDR

~

-. ~

7 e

".., ' ~. '..

~

  • ?!),1.;
H Raviced' 5/25/84 SCHEDULEDICOMPLETION DATES.FOR

{

v '

..NRC EP APPRAISAL APPENDIX A ITEMS ~

r i: P

' Scheduled.

Item Numbersa Item Completion Date>

1 i

445/8333-01

' Docket;the CEMPIand. corporate emergency plantipro-Complete f

?446/8317-01 icedures (CEPPs), or' delete the CEMP and incorporate-

~

i its provisions :into the CPSES emergencyL plan. -

i 445/8333-09..

IRevise'the emergency plan to include augmentation of 8/17/84 l.

~

~

f446/8317-09,

' emergency personnel:as.specified in NUREG-0654,.

l

' ~

' Revision 1, Table B-1, and provide _a method to-verify that there isi.a--reasonable' assurance that

~

,the augmentation. times can be met for the speci-

,fied minimum augmentation staff.-

[

N 1445/8333 Pursuant to the requirements of.NUREG-0737, Sup-

'6/29/84 l

L446/8317 -18 ~

. plement 1 Jand the' guidance contained in Regula-tory Guide:1.97, Table 2,;the applicant shall complete.the installation ~of. instrumentation in the control room toLassees plant ~and envircnmental-conditions duringLand following an accident..

+

i

~1 1445/8333-19' Complete training and qualification of control 9/7/84 j

s'

446/8317-19 room' personnel on all equipment used in-.the'de-h[,

tection," classification, notification, and. pro--

- tective' action assessment and recommendation-i prep' ration..

[

a r

i44'5/8333 Sufficient alternate.or backup power systems shall Complete l

,446/8317-281-

<be.provided to' maintain ~continuityz of TSC functions and to.immediately resume data acquisition storage, I

and. display ifiloss 'of : primary?TSC power occurss

~

445/8333-29 TSC radiation monitoring systems and the SPDS thct 9/7/84-x ; 446/8317--29 are;used for' emergency detection, classification, j

and assessment must.be fully installed,; tested,

-and made' operational..

(

[445/8333-30' TSC data L 11ection and evaluation systems'(RM-21) 8/31/84 g

(446/8317-30 that are used.in. accident _ assessment'and genera--

j tion of' protective action recommendation must be F

p

~

g fully.. installed, tested and made' operational.

le 144'5/8333-31 Emergency notification systems must be fully in-Complete' l

14.46/8317-31

' stalled, tested and made opera:ional.

l i

~

Vertical bar.on righthand margin indicates change e.g. item completed or scheduled completion date revised.

~

(1.

i

I

,.i Revisad 5/25/84 SCHEDULED COMPLETION DATES FOR NRC EP APPRAISAL APPENDIX A ITEMS

'i-Scheduled Item Numbers Item Completion Date l

'445/8333-32 Complete training and qualification of TSC person-9/7/84

'446/8317-32 nel on all equipment used in the classification, notification, and protective action assessment and recommendation preparation.

W

' The SPDS and the RM-21 that are used in the acci-8/31/84 1445/8333-38 446/8317-38 dent assessment and. generation of protective action recommmendations must be' fully installed, tested, and made. operational in the EOF.

l 445/8333-39

' Emergency notification systens (ENS ~and automatic Complete J446/8317-39

- ringdown) must be fully installed, tested and made operational..

445-8333-40 Complete, training and qualification of EOF person-9/7/84

~446/8317-40 nel on all equipment used in the classification, i

notification and protective action assessment and recommendation preparation.

2445/8333-43 Complete and test the gas sampling rig for high-Complete i

'~

446/8317-43 level grab samples from the vent' stack and dem-onstrate by drill or exercise that sampling and analysis can be complet'ed'in three (3) hours or

{

.less.

g:

1445/8333-50 Provide an operational decontamination facility Complete 1446/8317-50

.with' communications at the health physics control i

+

point and provide towels, communications and de-contamination agents and NOSF decontamination fac-

'I

ility.1 445/8333-60 Following the transfer of ARMS and PRMS:from the 8/31/84 I

L446/8317-60;

. vendor to the applicant, the applicant shall con -

i firm proper-instrument: maintenance, adequacy of_

l i

u -

operation, calibration checks, and prompt repair.

or.. replacement of inoperable instrumentation.

445/8333-65.

Complete. implementation of inspection, maintanance 7/16/84 446/8317-65, Land calibration procedures and provide appropriate

^

documentation of the new onsite meteorological measurements program, including identification of

- sensor types and spe'cifications, data reduction procedures, and determination of systen accuracies (compared to Reg. Guide 1.23) for staff review; also, provide inspection. maintenance and calibra-tion procedures for staff review as these are de-veloped and approved.-

e

iyl, ' j'.

Ravistd 5/25/84 SCHEDULED COMPLETION DATES FOR

-NRC EP APPRAISAL APPENDIX A ITEMS r

Scheduled

" Item Numbers Item Completion Date

'445/8333-66 Improve the-display of vertical temperature grad-7/16/84 446/8317-66:

ient in the' control. room by ~ installing charts with appropriate resolution.

445/8333-67' Modify EPP-302 to _ reflect :the information available Complete 446/8317 from the onsite meteorological measurements program 4
and specify the averaging time (15 minutes);

clearly establish the sources for.the hierarchy of substitution of meteor. logical data; eliminate cumbersome and/or poorly documented procedures; and' include specific provisions for updates.

.445'/8333-68 Provide a complete _ description of the arrangements 7/16/84

}446/8317-68

made withithe NWS to provide _ regional meteorological

. data > including. identification of the information to be-provided and the mechanism for; obtaining. updates 7

.of this'information.,

< 445/8333-69..

Provide equipment and/or-procedures for passive.

Complete-446/8317-69 notification of control. room shift personnel of' 1

severe weather conditions affecting or likely to affect the site.

1445/8333-84 Issue and approved EPP to control the use of'dedi-6/29/84 446/8317-84.

cated emergency vehicles with offroad capability

- which also provides protection for all transported Lemergency equipment and' instruments during adverse weather.

t 445/8333-89 Pursuant to the requirements of 10CFR50, Appendix Complete 1446/8317-89 E,(IV).(c), the applicant shall revise the emerg-ency plan and the EPP's to correctly differentiate

- between emergency classes and EAL's.

[445/8333-90--

Pursuant to the reqit'. cements of 10CFR50, Appendix Complete 446/8317-90:

E (IV).(c), the applicant shall. complete'as neces-usary readings from plant sensors that form the data L

sets of EAL's.

1445/8333-114' An evacuation notification system must be provided Complete 1446/8317-114; which can be detected by all persons in. owner-con-trolled areas including outdoor areas and the Ad-ministration Annex Building.

i i

5

__1.

7

..t,'..

4

,'.,7.;

Revissd f

5/25/84 i

4

-SCHEDULED COMPLETION DATES FOR

.NRC.EP APPRAISAL APPENDIX A ITEMS Scheduled

, Item Numbers-Item Completion Date i445/8333-115 Site-evacuation routes must be developed and the 7/27/84 1446/8317-115 applicant-shall provide a means to ensure that all personnel are aware of the' routes in an emergency.

c445/8333-116 Complete, implement and test a personnel accounta-8/21/84

446/8317-116

-bility system.

'445/8333-130 Complete the dissemination of emergency information Complete 1446/8317-130 to'the transient population.

445/8333-132-Conduct' additional training for control rooom per-6/29/84 446/8317-132'

.sonnel to ensure adequate knowledge of plant'oper-ating and emergency procedures and to-stress the e

requirement for compliance with~ procedures.

445/8333-133.

Condtict additional practica1' training for control 6/29/84

.446/8317-133-room personnel in emergency classification, empha-

-sizing EAL sets which have multiple conditions, to y-ensure that the watch: organization is able to dem-onstrate prompt and correct emergency classifica-tion skills.

445/8333-137

- Drills whichT require the use of EPP-302 should be 6/29/84,

1446/8317-137 conducted to improve.the efficiency by which the

-dose projection calculations are performed.

^

~445/8333-138 Train appropriate emergency response personnel ~on 9/7/84 446/8317-138-

-dose projection calculation. methods using-the RM-11 and RM-21 systems.-

~

1445/8333-139 Conduct practical drills with shift supervisors in 6/29/84 446/8317-139:

implementing the requirements of EPP-304 based on dose assessments and in communicating the results-of such' determinations to appropriate authorities.