Interim Significant Deficiency Rept Re Essential (safety- Related) Motor Control Ctrs.All Work Completed on Essential Motor Control Ctrs (Mccs) for Unit 1.Remaining 4 of 19 Ctrs Will Be Inspected by 840615
ML20091M395
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 05/24/1984
From: Tucker H
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8406110281
Download: ML20091M395 (1)


Text

DUKE Powen GOMPANY P.O. HOX 33180 CitARLOTTE, N.C. 28242 HALD. TUCKER Tetzenons

[fdj'$frp,j1984

( *) "~*"

,,,J,"l"_"'""

1l Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Re:

Catawba Nuclear Station Significant Deficiency No. SD 413-414/84-06

Dear Mr. O'Reilly:

This is to inform you that all work has been completed on the essential (safety-related) Motor Control Centers (MCCs) for Unit 1 as referenced in the subject report. Of the nineteen MCC's, inspection is complete for all but four, these hwing been delayed by testing. These four remaining MCC's will be inspected by June 15, 1984.

Very truly youre, h,N-

Hal B. Tucker LTP:dyh At.tachment cc: Director INPO Records Center Office of Inspection & Enforcement Suite 1500 U.' S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C.

20555 Atlanta, Georgia 30339 NRC Resident Inspector Mr. Robert Guild, Esq.

Catawba Nuclear Station Attorney-at-Law P. O. Box 12097 Palmetto Alliance Charleston, South Carolina 29412 2135 Devine' Street Columbia, South Carolina 29205

~

8406110281 840521 PDR ADOCK 05000413 S

PDR I

OFFICIAL OPY

,