ML20091K990
| ML20091K990 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 06/04/1984 |
| From: | George J TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | Jay Collins, Eisenhut D NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV), Office of Nuclear Reactor Regulation |
| References | |
| NUDOCS 8406070276 | |
| Download: ML20091K990 (77) | |
Text
_.
cl>
Y
.g TEXAS UTILITIES GENERATING COMPANY hMTWAY TOWEH
- jfM5 Nf)RTH OLIVE MTHEE*. L.H. M1
- IDA LLAN, TEA Am 7 5203 h0
~
et a es to A
go June 4, 1984 Mr. Darrell G. Eisenhut, Director Mr. John T. Collins, Regional Division of Licensing Administrator Office of Nuclear Reacto ' Regulation Region IV United States Nuclear Regulatory Commission United States Nuclear Regulatory Washington, D.C. 20555 Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Tx. 76012 Gentlemen:
The following information renresents our secor.d biweekly update on the status of important schedule related issues for Comanche Peak fuel load in late Sep-tember 1984.
Information contained in the attachments is the status through May 26, 1984.
Critical Path Implementation of a field change notice and associated prerequisite testing has moved Feedwater preop testing into the primary critical path status, caus-ing a potential nine day impact to fuel load.
Probability of recovery is high as work re-secuencing is developed and application of additional overtime.
The chemical and volume control system preop testing has slipped to a secon-dary critical path status causing a potential five day impact to fuel load.
Probability of recovery is very high as the actual preop testing started on 04/26/84.
Refurbishment of the diesel generators now stands as our third critical path.
Train A reassembly is complete and testing is proceeding on schedule, however, Train B reassembly has been delayed four days due to un-availability of NRR staff personnel to inspect components and observe reassem-bly within the confines of our schedule. The completion of Train B diesel is now expected for June 8,1984 with little chance of recovery.
Other Issues 1.
The following is the status for submitting Comanche Peak deferred pre-
/
operational testing items to be conducted after fuel load:
84060702'76 840604 O
/g 1
PDR ADOCK 05000445 g
j* (
l R
PDR g.
- u
,...........,,,-.....T.....-,.A.,
.,s
_ 1* * '
- Mr. Darrell G. Eisenhuti
. Mr.EJohn T. Collins -
- June 4,;1984 lPage 2
- A.
Items-Submitted-Main Steam Isolation Valves 5-16-84 Safety : Injection. Check, Valve Leakage.
5-29-84
- Containment-Cooling System-5-29-84 B.
Schedule for Submitting Remaining Items sProjectedLTransmittal Date Quantity 30-84 1
'6-07-84 2
6-14-84 2
2.
Present Craft Work Effort for Unit 1:
Manpower Unit 1 Building / Labor:
234 Rigging.
42 Paint 817 Pipe-121
- Insulation 72 M111 wright.
35 Fab / Hangers 108 Electrical.
335 s
Instrumentation 16 TOTAL 1,780 Attachments l '
Startup/ Testing Appendix A - D Master Data Base. Status Appendix E Paint Manhours - % Complete Appendix F.
Thermolag Appendix G & H
, wo
'q y:
L. i j. _ * *d '
- y.
^
N!
k
@[;<..
Mr. Da'rrell:Gi Eisenhut'
- Mr; John T;; Collins-
~ <
^.
~ June.4,.1984-
- Page'3,
. r-
- _ V--
s T
y fAv.
LIn conclu'sion,'s'ince our. May 21, ICM report, we have continued to make good l V c" 3.,
, progress to:our scheduled fuel ;1oad date in 1 ate September 1984. ' At this
-., ctime, we'know of:no new. issues that would preclude us meeting this objective.
Very ' ruly
,f 9
0 y/
- 3c f
^
.r I
=
A.
~
- JBGiljh' v
' Enclosure (s)
- cc: lT."Ippolito a
4.
N.-Reynolds 3
g
?
{4 d
I.
I
e s t
7;;
su
- g
- f.
+
I s
f<*'.
k i('
r i
I
F
,,l.:*':
STARTUP Status. Week Ending:.MAY.26,.~1984 TURNOVERS:
1Last Report This Report Total Accepted Total
. Accepted Subsystems 333
-313 333 316 REMAINING TURNOVERS:
Date Accepted Battery Pack Emergency Lighting Non-Safety Misc.-Cables to Felding Receptacles,
' Lighting, Etc..
05/17/84 Fire Detection-Panel, Detectors and Cables Control Building Tornado Dampers and Blowout Panels Misc.~ Signal Control Panel, Telephone Interface, Emergency Tone Gen. and Emergency. Alert Circuits
- Auxiliary. Building Tornado Dampers and Blowout Panels 05/16/84
-S.G. Building Tornado Dampers and Blowout Panels RCP Oil Collection System-
' Intermediate Range Detectors, Cables and Neutron 05/23/84 Detector Positioning Devices Power Range Cables and Detector Turbine Building Elevator I
-Containment Elevator Auxiliary Building Elevator
.N-16 Cables and Detectors' ERF Computer System Containment Access Rotating Platform Security Fence Co-Current Waste Low. Volume Waste I
Solid Waste Disposal Hoist Appendix A
r g
g
- e 9.
-c N
+
p e
5 J
'5
\\
$h I E%g wwE s
y a
e 5! = y s.p@.,
b C t
- )
\\
-e
's 5
3 9
i 8
E g
(N, D
hh
~
i s
e 5
's 's' la i
g
's s, N x.
o eoe N.
9 d
s a
s
__ 5,8 _
_s_
N.
8 w
m m
s
=
N d
N c
e o.
s s
W L
\\
c
-e e
's
-J s
n
-a-
\\ s,
-c s
%N
-* f s,
e g
's N
.k
-a
-e g n
-e N
-C-
-a
-e @
\\ -c z
-d 4 N3
- e
\\
5
-e 5'W:fE4775' 30 UN i i i l $ i l l l i'
$$$$iidiil O $ $ N O $
- g Appendix B V'
- 4l' s
. TESTING
SUMMARY
'(Last Report: MAY 12, 1984)
E FIELD TESTING.
RESULTS TOTAL' IN-PROGRESS COMPLETE APPROVED PREOPERATIONAL:,'
' ORIGINAL' (149 13 91 88
. RETEST--
29:
1 5
2 REPERFORM 23:
1 2
1
- ACCEPTANCE:
ORIGINAL-50 0
44 42 RETEST ~
7 3.
3 1
REPERFORM 16 2
5 4
-TOTALS
-274 20 153 138 TESTING
SUMMARY
(This Report: MAY 26, 1984)
FIELD TESTING PESULTS TOTAL IN-PROGRESS COMPLETE APPROVED PREOPERATIONAL:
. ORIGINAL-149 14 91 88 RETEST 31 3
9 4
REPERFORM 22 2
4 2
ACCEPTANCE:
ORIGINAL 50 0
44 42
-RETEST 7
1 5
1 REPERFORM 16 2
8 7
TOTALS 275 22 161 144 r
Appendix C
L A 9" 7
4 3
3 7
f 0
1 2
a 1
I. G w=.
e N
% 0'1 3
6 A
I.
A *>
i T
N T._.
S 0
l Ev
's 1
8 98 T
i 432 0
A T.x PI 2
R e_
E E.
C P
O N._
L "' '
A A.
E S
I.
A ~ s R
l I
E O t
F 4
P E_e; G'E l
D T p
C_o t
0 f
C.c A_S O"R 1 e
1 3
4
?'2 1U G fbU A t
i6 7
'2 o
i'2 L
9 3
i'1 U J
t8 9
2 ih 2
5 I't N
~
- U IA '.
e, s
11 s
s l
k 2
a t't e,
- Y s
D 2
't A L
I
,If 4
M E
WS f
L R
A PP I
N D
A G 7
S R WD 2
W H
J-t P
A G o
P K N1 S
4
'2 C
P S
A A
I T
S r
P A R
i E
M D G A
's E t 1
^
P t
(
r f A T
i P p A
E A i R nD f F f
(
A rT O O Pt P oS 6
C F
E E A
T L C
I L
t T
J U
o A sS D D D
S nCE E a
T T of H I
W.-
(
C C S S r f F E p f
S S a
=
'2 T T R 8 D D L E L S S L
I T A A T T
I N S S R
C C E
f W_-
N E E
- G GI E E J J A
D R R E E R u
- M I
I 1 T O
)
N O O R R P
^
G E
L s
aAA
^-4 e
~
d 0
0 0
0 0
0 0
0 0
0 O
a.
0 8
6 4
2 0
8 6
4 2
2 1
1 1
1 1
>@O3C X C L.4
_ 7, ;
...-1 m
MASTER DATA BASE STATUS:
l' Last Report Thit Report Unit 1 and Common' Total 8100 7400 NOTE:
The above tabulation includes Unit 1 and Unit 2 work items I'
_ remaining within the security boundary' established for Unit 1 1 operation.
i
~
We are currently engaged in establishing priorities of all work items which will include deferral of certain work items until
'after Unit 1 fuel load.. We' expect completion of this priortization activity by June 15, 1984 at which time this report will include a summary of Master Data Base items within the Unit 1 security boundary that are scheduled to be completed both prior to and after fuel load of Unit 1.
i l
Aopendix E
,..?*
PAINT MANHOURS AND MANPOWER: REACTOR CONTAINMENT BUILDING #1
. BASELINE MANHDURS ' ( APR 28,1984) TO COMPLETE CONCRETE: 60,500 MHS STEEL:
232,500 MHS EXPENDED WEEK (MAY 5)
EXP. TO DATE.
% TO DATE MANPOWER CONCRETE:
2363 MHS 2363 MHS 3.9 415 STEEL:
19149 MHS 19149 MHS 8.2 EXPENDED WEEK'(MAY 12)~
EXP. TO DATE
% TO DATE MANPOWER CONCRETE:
2860 MHS 5223 MHS 8.6 L
450 STEEL:
18060 MHS 37209 MHS 16.0 EXPENDED WEEK (MAY 19)
EXP. TO DATE
% TO DATE MANPOWER CONCRETE:
2098 MHS 7321 MHS 12.1 470 STEEL:
23289 MHS 60498 MHS 26.0 EXPENDED WEEK (MAY 26)
EXP. TO DATE
% TO DATE MANPOWER CONCRETE:
1869 MHS 9190 MHS 15.2 520 STEEL:
21457 MHS 81955 MHS 35.2 T
l l
Appendix F
e j-
-gp 7,p:;
Q,;
l e, a ;.
- t m
A
- ,=
.s.
. THERM 0 LAG t..
I Ltg l
BASELINE'(MAY 12,' 1984) TO COMPLETE.
- REMAINING: '23,600 SQUARE FEET
~
4
)
MANPOWER: '160 PEOPLE STATUS WEEK ENDING (MAY 26,1984),
' REMAINING: -- 13,285 SQUARE'. FEET '
- MANPOWER
- 166 PEOPLE.
a
,..'4
- k:
t s
e
. 't.
1 Appendix G E
I, 65,000 60,000 1
l
,1 50,000 p 40,000 w
W l
U/WK.
CURRENT RATE 5,000 W 30,000-i EE is 4
$U0 x
20,000
\\
\\
10,000
\\
\\
\\
\\
JAN FEB MAR APR MAY JUN THERMOLAG
_