Text
.
s t
P.o. box 5000 - CLEVELAND, oHlo 44101 - TELEPHCNE (216) 622-9800 - ILLUMINATING OLDG.
- 55 PUBLICSOUAHE H E C L E V E lli ti b E
E C T !? l:
lLLUici !.
T;
- a Serving The Best Location in the Nation MURRAY R. EDELMAN VICE PRESIDENT NUCLEAR May 29, 1984 PY-CEI/NRR-0117 L Mr. B. J. Youngblood, Chief
' Licensing Branch No. 1 Division of Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555 Perry Nuclear Power Plant, Units 1 & 2 Docket Nos. 50-440; 50-441 Piping Design Review
Dear Mr. Youngblood:
This letter is to provide you with a copy of the final report on the Piping Design Review program. This program was discussed with the NRC staff on March 12, 1984 and in our April 5, 1984 letter (PY-CEI/NRR-0103 L).
The piping design review program was undertaken as one element of the overall Design Verification ef fort.
This final report consists of two parts.
Part I describes the overall program, CEI's review of the consultant's (Cygna Energy Services) observations and our evaluation of generic implications. Part II is the final report of the consultant's detailed review of selected piping systems. (Volumes 1 and 2).
Based on this combined review eifort, and the resulting programs that are underway and being tracked to resolve the observations and generic concerns, CEI believes that the mechanical design adequacy at the Perry Nuclear Power Plant is assured.
We hope that this information is helpful in the development of any initiatives you may plan.
If you have any questions please contact us.
Very truly yours, Murray R. Edelman Vice President Nuclear Group MRE:nje s
Attachments cc: Jay Silberg, Esq.