NRC-84-83 WISCONSIN PUBLIC S E RVICE CO RPORATIO N P.O. Box 1200, Green Bay, Wisconsin 54305 4
May 18, 1984 Mr. C. J. Paperiello, Chief Emergency Preparedness and Radiological Safety Branch U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137
Dear Mr. Paperiello:
Docket 50-305 Operating License DPR-43 Kewaunee Nuclear Power Plant IE Inspection Report 84-03 (DRMSP)
The attachment to this letter details our response to the one item of non-compliance identified in Inspection Report 84-03 (DRMSP).
Very truly yours,
& 0. )cU h Carl W. Giesler Vice President - Power Production JLB/js
- Attach, cc - Mr. Robert Nelson, US NRC Mr. S. A. Varga, US NRC 8406050347 840529
{m^t gDRADOCK05000g p
NRC10-11.2
~
ATTACHMENT Response to Item of Noncompliance IE Inspection Report 84-03 (DRMSP)
Violation:
Technical Specification 6.11 requires that radiation control procedures be main-tained and adhered to for all operations involving personnel radiation exposure.
Administrative Control Directive (ACD) 13.2 requires that plant staff and contractor personnel be given respiratory protection training in accordance with ANSI Z88.2-1980.
Contrary to the above, according to licensee and contractor personnel, the training specified in ANSI Z88.2-1980 was not consistently given to contractor personnel who wore respirators.
Response
Wisconsin Public Service Corporation acknowledges the non-compliance as described. The requirement in ACD 13.2 that respiratory training be given in accordance with ANSI Z88.2-1980 has been discussed with the appropriate indivi-duals involved.
The Training Department is presently performing an upgrade of respiratory pro-tection training given to contractors who require the use of respirators. This training is to be presented during the indoctrination process as contractors arrive and are identified as having the need to wear respirators on the job.
It is anticipated that these modifications to the respiratory protection training program will be completed prior to August 1, 1984, at which time WPSC will consider itself in full compliance.
.~.