ML20091H767

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in IE Insp Rept 50-410/84-02.Corrective Actions:Advance Project Change Notices Will Be Issued Identifying Specific Considerations to Delay Implementation of Revised Quality Std
ML20091H767
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 04/26/1984
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20091H758 List:
References
NMP2L-0041, NMP2L-41, NUDOCS 8406050284
Download: ML20091H767 (3)


Text

_

Y NIAGARA NuMOHAWK NIAGARA MOHAWK POWER CORPORATl0N/300 ERIE BOULEVARD WEST, SYRACUSE, N Y.13202/ TELEPHONE (315) 474-1511 April 26,1984 (NMP2L 0041)

Mr. R. W. Starostecki, Director U.S. Nuclear Regulatory Commission Region I Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re: Nine Mile Point Unit 2 Docket No. 50-410

Dear Mr. Starostecki:

Your Inspection Report No. 50-410/84-02 dated March 23, 1984 identified one apparent violation resulting from an inspection conducted at the Nine Mile Point Unit 2 construction site. Niagara Mohawk's response is enclosed.

Very truly yours,

~._

S

,C. V. Man

.Vice President Nuclear Engineering & Licensing CVM/TL:ja Enclosure xc: Mr. R. Gramm, Resident Inspector ohk[o PDR

NIAGARA M0 HAWK POWER CORPORATION NINE MILE POINT UNIT 2 DOCKET NO. 50-410 Response to Notice of Violation Attached to NRC Inspection Report 84-02 The apparent violation was identified as follows:

As a result of the inspection conducted on February 7 and 9,1984, and in accordance with the NRC Enforcement Policy (10CFR2, Appendix C) published in the Federal Register on March 9,1982 (47FR9987), the following violation was identified:

10CFR50, Appendix B, Criterion VI, requires "...that measures shall ensure that documents, including changes, are reviewed for adequacy and approved for release by authorized personnel and are distributed by authorized personnel..." Stone & Webster nonconformance and disposition report (N&DR) specified in Quality Stanoard (QS-15.1)

Revision B, dated December 20, 1983, lists the N&DR form to be used for this site with a detailed procedure for filling in the various blocks of the N&DR form.

Contrary to the above, as of February 9,1984, and at least since April 6,1983, the N&DR form being used at this site is not the document listed in the QS-15.1 standard.

Also, the instruction for filling out the N&DR form in QS-15.1 is not. compatible with the N&DR form presently being used by Stone & Webster's Qu lity Control organization.

This is a Severity Level IV violation (Supplement II).

The following is submitted in response to this item of nonconformance.

Stone & Webster Engineering Corporation's Quality Standard No. QS-15.1, Revision A, Change 2 was the only approved Quality Standard in effect between February 10, 1982 and January 15, 1984, for reporting Stone &

Webster nonconformances on the Nine Mile Point Unit 2 Project. During the period in question, Nonconformance and Disposition Report form NM-001 was used on the project.

(In accordance with QS-5.1, Revision E, an Advanced Projcct Change Notice ( APCN) was issued to allow the use of the project-specific fann NM-001.)

This form was implemented in response to Nuclear Regulatory Commission Inspection Report 81-10, unresolved item 81-10-01.

On January 16, 1984, Revision B, Change 1 of QS-15.1 became effective.

However, because this revision to the Stone & Webster Engineering Corporation corporate Quality Standard (QS) was issued prior to Niagara Mohawk management approval, the new form was not immediately implemented.

This is an isolated incident of not implementing a revision to a procedure in a timely manner.

On February 8, 1984, instructions were issued by the Stone & Webster Engineering Corporation Project Quality Assurance Manager that effective February 10, 1984, the new form (5040.235) contained in QS-15.1, Revision B, Change I would be used in processing nonconformances at the site.

In the future, an Advance Project Change Notice (APCN) will be issued identifying specific project considerations to delay implementation of a revised Quality -Standard (QS).

m