Interim Deficiency Rept DER 83-75 Re Improperly Torqued Bolts,Supplied by Foxboro,Securing Two D01265A Panel Filler Assemblies.Initially Reported on 831123.Final Rept Delayed Until 840629
ML20091H724
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 05/23/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-29583-TDS, DER-83-75, NUDOCS 8406050267
Download: ML20091H724 (2)


Text

l4 y..

iEEiVEu Arizona Public Service Compan"yE" P o. box 21666. PHOENIX. ARIZONA 85036 EG '"" 29 n: 2 ! C May 23,r1984.,...

ANPP-2955ETDS/TRB

.U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T._W.

Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Time Extension For Report - DER 83-75 A 50.55(e) Potentially Reportable Deficiency Relating To Bolts Securing The Two D0126SA Panel Filler Assemblies, Supplied By Foxboro, Were Improperly Torqued File:

84-019-026; D.4.33.2

Reference:

(A) Telephone conversation between R. Dodds and R. Tucker on November 23, 1983 (B) ANPP-28361, dated December 5,1983 (Interim Report)

(C) ANPP-28663, dated January 23,1984 (Time Extension)

(D) ANPP-28918, dated February 22, 1984 (Time Extension)

(E) ANPP-29284, dated April 12, 1984 (Time Extension)

Dear Sir:

The NRC was notified of a ptentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B), and Time Extensions were requested by References (C), (D), and (E). At that time, it was estimated that a Final Report would be available by May 25, 1984.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by June 29,1984, at which time a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours O AA_

C E. E. Van Brunt, Jr.

APS Vice President, Nuclear ANPP Project Director EEVB/TRB:ru cc:. See Page Two 84060 267 840523

~

/[-2. 7 l 8 @

PDR CK 05000528 5

S

.PDR

.,y.

...e Mr. T. W. Bishop

- DER 83-75

'Page Two-cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

D. B. Karner W. E. Ide D. B. Fasnacht A. C. Rogers

~B. S. Kaplan L. A. Souza D. E. Fowler J. Vorees J. R. Bynum J. M. Allen P. P. Klute A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson L. E. Vorderbrueggen s

G. A. Fiore111 S. R. Frost J. Self D. Canady_

Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, GA 30339 4

-. - ~ -,

y-

-v_-.,

.., <,. -,~-.