Updates RO 369/83-20 Re Discrepancies in Initial Integrated Leak Rate Test.Procedural Change to Soap Bubble Test of Penetration Flued Head to Guard Pipe Welds While Containment Pressurized,Will Be Incorporated Prior to Next Testing
ML20090M726
Person / Time
Site: McGuire Duke Energy icon.png
Issue date: 05/14/1984
From: Tucker H
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
RO-369-83-20, NUDOCS 8405290150
Download: ML20090M726 (1)


Text

Dmce POWER COMPINY P.O. BOX 30180 oHAIU.OTTE, N.o. 28242 H t.1 B. TUCKER TELEPff0NE

_ ** "/,","*" . May 14,1984 (704) ara-4sai l

i l

Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear. Regulatory Commission  !

Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303

Subject:

McGuire Nuclear Station, Unit 1 Docket No. 50-369 LER/RO-369/83-20

Dear Mr. C'Reilly,

My letter of May 17, 1983 submitted reportable occurrence report.RO-369/83-20 which dealt with discrepancies in the Unit 1 Initial Integrated Leak Rate Test.

As part of the corrective actions given in the report it was stated that a procedural change will be incorporated in the 4010 month Surveillance Test to cover Technical Specification 4.6.1.2f, detailing the Soap Bubble Test of hot penetration flued head to guard pipe welds while containment is pressurized.

This change was originally to be incorporated in the Unit 1 procedure by 6/15/83; however, the change will now be incorporated prior to performance of the next surveillance testing.

Very t'ruly yours, b- l$

Hal B. Tucker -

PBN:glb cc: Document Control Desk Records Center U. S. Nuclear Regulatory Commission Institute of Nuclear Power Operations-Washington, D. C. 20555 1100 circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 Mr. W. T. Orders NRC Resident Inspector McGuire Nuclear Station f