Final Deficiency Rept DER 83-54 Re Washers Found in Steam Generators 1 & 2.Initially Reported on 830802.Loose Parts Will Be Removed from Generators.Not Reportable Per 10CFR50.55(e) Requirements
ML20090L288
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 01/17/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
Shared Package
ML20090L275 List:
References
FOIA-84-212 ANPP-28632-BSK, DER-83-54, NUDOCS 8405250278
Download: ML20090L288 (4)


Text

{{#Wiki_filter:, . O 1 lC rs

 .                                      Arizona Public Service Company                 pggyr.c l                                        Po Box 21666 e PHOENIX. ARIZONA 85036          ,a t ' "

January 17,16n J.C 23 R! D I ANPP-28632-BSK/TRB RI.a3 U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Final Report - DER'83-54 ] A 50.55(e) Reportable ' Condition Relating to Washers Found In Unit 1 Steam Generators #1 and #2. File: 84-019-026; D.4.33.2

Reference:

A) Telephone Conversation between P. Narbut and R. Tucker on August 2, 1983 B) ANPP-27603, dated August 22, 1983 (Interim Report) (~ C) ANPP-28009, dated October 13, 1983 (Time Extension) D) ANPP-28461, dated December 19, 1983 (Time Extension)

Dear Sir:

At tached is our final written report of the deficiency referenced above, which has been determined to be Not Reportable under the requirements of 10CFR5 0.5 5(e) . Very truly yo , W Ok t E. E. Van Brunt, Jr. APS Vice President, Nuclear ANPP Project Director EEVB/TRBaru Attachment cc: See Page Two 8405250278 840423 PDR FOIA PDR BERNABE84-212 g d io

s (~) ) - cs i

          -                 Mr. T. W. Bishop DER 83-54 Page Two cc:                                Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. C. Woods, Jr.

J. A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees

    .                                                          J. R. Bynum P. P. Klute A. C. Gehr W. J. Stubblefield W. G. Eingham R. L. Patterson

(' R. W. Welcher H. Foster

                                         .                     D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiore111 S. R. Frost J. Self D. Canady Records Center                                                                                        ,

Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, GA 30339 i r I ('

                       .                      o                                   >
   .                                               FINAL REPORT - DER 83-54 k                                           DEFICIENCY EVALUATION 50.55(e)

ARIZONA PUBLIC SERVICE COMPANY (APS) PVNGS UNIT 1-I. Description of Deficiency Inspection af ter hot functional testing revealed that various loose parts (i.e., washers and a 3 inch type plug) were found in Unit 1 Steam Generators No. I and No. 2. It has been determined that the loose parts came from Combustion Engineering (C-E) temporary instrumentation hardware installed inside the Reactor Pressure Vessel (RPV) on the Core areas. This instrumentation was used to provide baseline data during the ' Pre-Critical Vibration Monitoring Program (PVNP). The 4 instrumentation was removed from the RPV af ter completion of the test. II. Analysis of Safety Implications Bechtel requested assistance from C-E in evaluating and dispositioning this condition and concurs with the attached CE disposition that the condition is not safety significant. The temporary instrumentation hardware size and material selection was

           ~

based on worst case hardware breakaway, so. that vital areas of the Steam Generators would not be harmed by this condition. Also, the testing flow parameters indicated that any loose parts would be

                          ' trapped and easily removed upon completion of the PVMP. Therefore, this condition is evaluated as not reportable under the requirements of 10CFR50.55(e).

III. Corrective Action

                    -               A. Loose parts will be removea from Unit 1 Steam Generators No. 1 & 2. NCR SM-2435 will refer to DER 83-54 and be dispositioned based on this corrective action.

B. The RPV and remainder of the PCS system will be inspected for loose parts after RPV head rencval. C. Action to preclude recurrence is not applicable since the PVMP will only he performed in Unit 1 (Reference V-CE-15987, dated 2/26/82). C

s e ' '
          . V .*   .       .                                                  r"
 .     .,.   *c. '.               Ch-- * . C( )       MTACMENT TO DER 63-54 g )

r: ., p ,

   \T .; POWER                                                                                     '
           <     n     ; SYSTEMS                                         September 9, 1933 -           : ; .. .c-- -        -

V-CE-18986  : - Mr. W. G. Eingham f.~ ^_.7 ' ' ' -;;,,1.,. Eeci.tel Pcwer Cerperation .

                                                                                                       --iY,'                    ,

12400 East Imperial Highway Ncrwalk, CA 90650

                                                                                                      --{'"=             -

7;

                                                                                                                  , . .    -- i

Subject:

Stea Generater Bevel Washers and Plug . . . . DER 83-54 (Unit 1). t '), .... .

                                                                                           ;- __._at                             ,

Reference:

Eechtel letter B/CE-E-45597 7J; , dated August 5, 1983 yy .- [

                                                                                                          .s t C

Dear Mr. Bin 6 ham:

9'<' 7 Z The cerditiens listed in the subject DER, received by Reference (A) .have r er_. T review 2d and the fellewing is eur evaluatien as to the reportability in acccrdance with 10CFR 50.55(e). It has been deter ~:ined that the leese parts care frem temperary instru .er.tatien irstalled fer data acquisitien during pre-service testing. B e calfuretien cf si .a will ret jeepardize eperatien er the Steam Generaters. We Icese parts will impact the primary head and tubesheet in a ccepletely rardem manner therefere, repeatedly striking the same peint is extremely unlikely and there will be no expesure of base tetal. h e tubes are recessed (,, in the tubesheet therefere the size of the leese parts preclude them damaging any of t.he heat transfer surface. The material of the leese parts is cer.patible with the clad en the primary head so that there will be no cerresive effects. . In CE's epinien, the deficiency is cet repertable under 10CFR 50.55(e). CE's evaluaticn was perfermed in acccrdance with eur Quality Assurance er Cesign Mar.ual as indicated by FAR No. 14273 -958 (Unit 1). These decuments are available fer review at the CE Windsor effice. Very truly yeurs, C. Fergusen Project Manager CF/JJS/mr cc: Messrs: E. E. Van Brurt, Jr. G. C. Andegnini J. Verees

  • W. H. Wilsen R. H. Helm J. W. Dilk *
        '                            G. A. Butterwerth S. N. Mager D. B. A..erice W. L. "rlbrald J. R. Byrum
                                                     .}}