Interim Potentially Reportable Deficiency Rept DER 83-66 Re Internal Problems in Motor Driven Auxiliary Feedwater Pump. Initially Reported on 831011.Addl Time Required.Final Rept Will Be Submitted on 840601
ML20088A815
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 03/22/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-29128-BSK, DER-83-66, NUDOCS 8404130160
Download: ML20088A815 (2)


Text

-

L

,;ts Arizona Public Service Company March 22, 1984 ANPP-29128-BSK/TRB U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lace - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Time Extension For Report - DER 83-66 A 50.55(e) Potentially Reportable Deficiency Relating To Internal Problems In Unit 1 Motor Driven Auxiliary Feedwater Pump.

File: 84-019-026; D.4.33.2

Reference:

(A) Telephone conversation between P. Narbut and R. Tucker on October 11, 1983 (B) ANPP-28199 dated, November 8, 1983 (Interim Report)

(C) ANPP-28615 dated, January 13, 1984 (Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), and an Interim Report was transmitted by Reference (B),

and a Time Extension by Reference (C). At that time, it was estimated that_a Final Report would be available by March 29, 1984.

Due to the extensive investigation and evaluatioa required, it is note expected that this information will be finalized by June 1,1984, at which time a complete report will be submitted.

There is.no new information or change to the Interim Report at this time.

Very truly yours,

{

Ct LL 4LL-E. E. Van Brunt, Jr.

gh APS Vice President, Nuclear 7

> d. fiO!9;gANPP Project Director EEVB/TR8tdb L E :ll liy o g g ag $ U,

cc: See Page Two c,

h e.

lE-2?

u

o.,-

c Mr. T. W. Bishop DER 83-66 Page Two cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. C. Woods, Jr.

W. E. Ide D. B. Fasnacht A. C. Rogers B. S. Kaplan L. A. Souza J. Vorees J. R. Bynum P. P. Klute A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Pa tterson R. W. Welcher H. D. Foster i

D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiore11i S. R. Frost J. Self D. Canady Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, CA 30339 I

I 1

%