DUKE POWER GOMPANY-P.O. BOX 33189 CHARLOTTE, N.C. 28242
. HAL B. TUCKER n,,,,,,,o n
~~
2 Alf; gg March 4
Mr. James P. O'Reilly, Regional Administrator U.:S._ Nuclear Regulatory Commission
- Region II
.101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Re: ' Catawba Nuclear Station Units 1 and 2
' Docket Nos. 50-413 and 50-414
Dear Mr. O'Reilly:
In my -letter of February 1,1984 concerning replacement of undersized motor operators for Westinghouse valves (Significant Deficiency Report No.
SD 413-414/82-09) it was stated that work would be completed for Unit I and Unit 2 by April'1,-1984. Due to the extension of ESF_ testing, which involves two remaining valves on Unit 1, the expected completion date for this deficiency will be April 16, 1984.
Very truly_yours, Ak_,--_
Hal B. Tucker LTP/php cc: ' Director INP0 Records Center Office of Inspection & Enforcement Suite 1500 U. S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C. 20555 Atlanta, Georgia 30339 NRC Resident Inspector Mr. Robert Guild, Esq.