Interim Deficiency Rept Re Replacement of Undersized Motor Operators for Westinghouse Valves.Due to Extension of ESF Testing,Involving Two Remaining Valves on Unit 1,expected Completion Date for Deficiency Will Be 840416
ML20087N879
Person / Time
Site: Catawba  
Issue date: 03/29/1984
From: Tucker H
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8404050127
Download: ML20087N879 (1)


Text

m_

DUKE POWER GOMPANY-P.O. BOX 33189 CHARLOTTE, N.C. 28242

. HAL B. TUCKER n,,,,,,,o n

~~

2 Alf; gg March 4

Mr. James P. O'Reilly, Regional Administrator U.:S._ Nuclear Regulatory Commission

- Region II

.101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Re: ' Catawba Nuclear Station Units 1 and 2

' Docket Nos. 50-413 and 50-414

Dear Mr. O'Reilly:

In my -letter of February 1,1984 concerning replacement of undersized motor operators for Westinghouse valves (Significant Deficiency Report No.

SD 413-414/82-09) it was stated that work would be completed for Unit I and Unit 2 by April'1,-1984. Due to the extension of ESF_ testing, which involves two remaining valves on Unit 1, the expected completion date for this deficiency will be April 16, 1984.

Very truly_yours, Ak_,--_

Hal B. Tucker LTP/php cc: ' Director INP0 Records Center Office of Inspection & Enforcement Suite 1500 U. S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C. 20555 Atlanta, Georgia 30339 NRC Resident Inspector Mr. Robert Guild, Esq.