r O PSEG Pubhc Serwce Electnc and Gas Company P O. Box 23G Hancocks Bndge. New Jersey 08038 Nuclear Department March 6, 1984 Dr. Thomas E.
Murley, Regional Administrator Region I U.
S.
Nuclsar Regulatory Commission 631 Park Avenue King of Prusnia, Pennsylvania 19406
Dear Dr. Murley:
NRC INSPECTION 50-311/83-18 SALEM GENERATING STATION UNIT NO. 2 MAY 9-18, 1983 During the subject inspection, one violation was identified related to a failure to establish a vent path upon loss of the Pressurizer Overpressure Protection System (POPS).
Public Service Electric and Gas responded to this violation by letter dated October 26, 1983.
In response to subsequent discussions with the Salem Senior Resident Inspector, provided below is a supplemental response to the violation.
Changes from our October 26, 1983 response are noted by a vertical line on the right-hand margin.
ITEM OF VIOLATION In accordance with the NRC Enforcement Policy, 10 CPR Part 2, Appendix C, the violation is set f orth below:
Technical Specification limiting condition for operation 3.4.10.3 requires that, with the Reactor Coolant System (RCS) less than 312*F and the vessel head in place, two Pressurizer Overpressure Protection System (POPS) relief valves shall be operable or the RCS shall be depressurized with an RCS vent of greater than or equal to 3.14 square inches.
With both POPS valves i nope ra ble, the RCS is to be depressurized and vented within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.
Contrary to the above:
Between 6:00 a.m.
on April 24, 1982, and 2:00 p.m.
on April 25, 1983 with the RCS less than 312*F and the vessel head in place at Unit 2, both POPS valves were inoperable, and the RCS was not depressurized with a designated RCS vent of greater than or equal to 3.14 square inches.
8403300196 840323 The Energy People PDR ADOCK 05000311 G
PDR 9% 2168 Mw 11 P2
P' or. Thomas E.
Murley, Regional Administrator U.S.
Nuclear Regulatory Commission 3/06/84 Reply to Item A The loss of the RCS vent path was due to a f ailure between the Shift Supervisor and Maintenance Supervisor to follow the established plant procedure of approving all work orders only in writing, and only at the time the work is actually to be accomplished.
Another contributing factor was that no formalized procedural guidance existed to indicate how the RCS vent path should be established and controlled.
a.
Corrective steps which have been taken and results achieved Upon discovery of the loss of vent path, immediate steps were initiated to establish an alternate vent path.
The path was established at 1358 hours0.0157 days <br />0.377 hours <br />0.00225 weeks <br />5.16719e-4 months <br />, April 25, 1983.
The Shift Supervisor was counseled in regard to his actions in the matter.
A night order book entry was made to assure all Operations Supervisors are aware that work orders should not be approved until the plant is in a condition to allow the work to proceed safely.
Operations Department Directive OD-70, Installation / Removal of PORV Blocking Devices, and OP-II-2.3.6 and OP-II-2.3.7, Establishing and Terminating Reactor Coolant System Vent Path to the Pressurizer Relief Tank, were developed, and issued on June 29, 1983.
They provide a formalized method to establish, terminate and control the RCS vent path when it is required by Technical Specifications.
AP-9, Control of Station Maintenance has also been revised to require that only one major task be performed per individual work order to preclude multiple tasks from creating uncontrolled conditions in the plant.
All Maintenance Supervisors were also reinstructed on the importance of keeping the operating shift informed of maintenance as it affects plant status, b.
Corrective steps which will be taken to avoid further violations The Maintenance Department will send all its supervisors to the Supervisory Skills Training Program, which includes a two week course on PWR fundamentals.
I l
Dr. Thomas E. Murley, Regional Administrator U.S.
Nuclear Regulatory Commission 3/06/84 c.
Date when full compliance will be achieved We are presently in full compliance with Specification 3.4.10.3.
Sincerely, E.
A.
Liden Manager - Nuclear Licensing and Regulation CC:
Mr. Donald C.
Fischer Licensing Project Manager Mr. James Linville Senior Resident Inspector l