Informs That All Q Redline Drawings Incorporated,Per Hold Point 001,Rept 6
ML20087L095
Person / Time
Site: Midland
Issue date: 03/15/1984
From:
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
STONE & WEBSTER, INC.
References
CSC-7465, NUDOCS 8403270023
Download: ML20087L095 (2)


Text

-

Y_,

A/118 s*..

CONSUMERS' POWER COMPANY MIDLAND ENERGY CENTER Transmittal. No:

CSC-7465 Date: March 15,1984 To:

Stone & Webster P O Box 1963 Midland, MI 48640

/ PRINCIPAL STAFF Attached Is :

Partial Response To

,fM*. KOS DPRP

~

D/RA JE Complete Response To-RA For Your Information O

ENF Fi19 dgS Other 4

==

Description:==

Hold Point 001, Report No. 6 - All "Q" redline drawings have been incorporated (reference Becthel letter BCCC-9136 dated March 14, 1984 attached).

-A//kSignature: '

j

[JGKeppler, NRC> RegionlIII /w/a' "

cc:

JJHarrison[NRC' Region III w/a RJCook, NRC Site w/a RAWells, MPQAD w/a BHPeck, }EC w/a NIReichel, MEC w/a DDJohnson, FEC w/a g3hh[0 sai4

m C :=

Bechtel Power Corrporation Post Othee Box 2167 Micfand, Michigan 48640 March 14, 1984 Consumers Power Company P.O. Box 1963 Midland, Michigan 48640 Attention:

D. L. Quamm4 Site Manager Midland Plant Units 1 la 2 Bechtel Job 7220 STONE AND WEBSTER REPG1RT NO. 6 (S&W 15)

BCCC-9136 Cear'Mr'. Quamme:

Reference:

1.

CPCo letter CSM-0666 to Stone & Webster dated August 9,1983.

2.

Bechtel letter BCCC-9027 to Consumers Power Co. dated Februa.ry 21, 1984.

This is Construction's complete response to Stone and Webster Rgport No. 6

- (S&W 15) concerning adequacy of drawings.

All -instrumentation redline drawings reported in reference 2 have been incorporated. This completes the incorporation of all "Q" redIt71e drawings for the' Project.

If you have any questions, please contact John Russell at Extension 7594.

Very truly yours,

)

G. A. Hierz Site Manag r i