Special Rept:On 950223,Free Field,60 Feet Below Grade Seismic Sensor Failed.Caused by Vibrations Induced from Road Work Performed in Support of on-site Const.Decided Not to Restore Sensor Until Completion of Road Work on 950414
ML20087G245
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 03/27/1995
From: Hovey R
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9504040033
Download: ML20087G245 (1)


Text

y:

. O PSEG Public Service Electric and Gas Cornpany P.O. Box 236 Hancocks Bridge, New Jersey 08038 Hope Creek-Generating Station j

J March 27, 1995 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Dear Sir:

Hope Creek Generating Station Locket No. 50-354 Unit No. 1 Special Report 95-02 This Special Report is being submitted pursuant to the requirements of Hope Creek Technical Specification 3.3.7.2 -

Action a, due to one seismic monitoring instrument channel being inoperable for more than 30 days.

On 2/23/95, the Free Field, 60' below grade seismic sensor failed due to vibrations induced from road work being performed in support of on-site construction.

Due to the likelihood a new sensor would ultimately fail while construction activities are ongoing, it was decided not to restore the Free Field sensor until completion of the road work currently scheduled for 4/14/95.

All remaining seismic monitorilig channels are operable and have not been affected by the road work.

Instruments and Controls department personnel are prepared to replace the sensor when the road work is completed.

Sincerely,

_L R.J. Hovey General Manager -

Hope. Creek-Operations LA/

C Distribution 040019

'k The Energy People 9504040033 950327 PDR ADOCK 05000354 S