ML20087G058

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Leaking Check Valves.Initially Reported on 840206.Constructor/startup Interface Examined to Assure Controls Exist to Identify & Track Incomplete Items
ML20087G058
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 03/07/1984
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
KMLNRC-84-027, KMLNRC-84-27, NUDOCS 8403190316
Download: ML20087G058 (2)


Text

_ _ _ _

KANSAS GAS AND ELECTRIC COMPANY TPE ELECTAC COMPANY GLENN L KDESTER vect ents@th? - NucLEam March 7, 1984 3M@20WM ih Mr. J.E. Gagliardo, Acting Ch3ef

}((

Rea: tor Projects Branch 2 s

U.S. Nuclear Regulatory Commission M -9 m Region IV ei,*

611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 KMLNRC 84-027 Re:

Docket No. STN 50-482 Subj: Potential 10CFR50.55(e) Interim Report -

Leaking Check Valves

Dear Mr. Gagliardo:

This letter provides an interim report on a potentia L 10CFR50.55(e) concerning leaking check valves at Wolf Creek Generating Station.

This matter was initially reported by Mr. Otto Maynard of Kansas Gas and Electric Company (KG&E) to Mr. Michael Murphy of the Nuclear Regulatory Commission, Regien IV, on February 6,1984.

While filling the primary system it was noted that a check valve in the high pressure coolant injection (EM) system was leaking.

In-vestigation revealed that the valve had been disassembled and since a new gasket was not available, the bonnet bolts had only been " snug" tightened until the valve could be reassembled with a new gasket. The existing condition of the valve was documented on its traveler, but was not identified on the Turnover Exception List. A doctunentation review was initiated to detcrmine if other valves could have been affected in a similar manner. Documentation packages for approximately nine hundred valves were reviewed. This review revealed a total of nine valves with incomplete work not previously identified on the Turn-over Exception List. Seven of the nine valves were awaiting new gaskets for reassembly and the other two had the internals removed to support flushing activities. Although Special Instruction Sheets for these valves contained the correct information, this information was not properly transferred to the Turnover Exception List.

An investigation to determine the cause of these discrepancies resulted in the review and revision of procedures, ensuring that adequate measures exist to identify incomplete work. Other travelers addressing similar items are currently being reviewed for completeness. Any incomplete work and/or documentation identified will be listed on the appropriate Turnover Exception List.

In addition to the above described actions, 8403190316 040307 PDR ADOCK 0500C482

/b S

PDR l 0 201 N. Market -Wichita, Kansas - mar Address: PO. Sn 208 i Wichita, Kansas 67N1 - Telephone: Area Code (316) 261-6451

[

.o-1

.s I

j.

Mr. J.E. Gagliardo KMLNRC 84-027

-2 March 7, 1984 the Constructor /Startup interface is being examined to assure that controls exist to identify and track incomplete items.

The status of this potential 10CFR50.55(e) will be carried on the monthly status update as file 53564-K122. The final report or any significant new information will be submitted by separate correspondence. In the interim, please direct any questions concerning this subject to me or to Mr. Otto Maynard of my staff.

Yours very truly, pr Glenn L. Koester Vice President - Nuclear GLK:bb cc: RCDeYoung WSchum