Informs of Discrepancies Noticed in Const at Facility. Discrepancies Presently More Serious Due to Util Trying to Meet Fuel Load Schedule
ML20086Q434
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 03/12/1973
From: Jain M
BECHTEL GROUP, INC.
To: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20086Q423 List:
References
NUDOCS 8402270547
Download: ML20086Q434 (1)


Text

( -. . . . - - .- 1 - . -- -

o o Bechtel Corporation Engineers-Constructors Fif ty Beale Street ,

San Francisco, California 94119 March 12, 1P_73 Mr. Eldon J. Brunner Facilities Test & Startup Branch Atomic Energy Co:stimion

Dear sir,

Will you let me know if it is wisc for me to report to your office discrepancies which I noticed in the construction of this project, which should not appear especially in a nuclear plant. As a responsible engineer, I feel it my duty to report this matter to your office. It is worst now since the owner, PECO is trying to meet their 8' fuel load schedule". Please treat this matter confidentially.

Sincerely yours, 7t Mohan R.hJn Start-up Engineer Peach Bottom Nuclear Plant Delta, Pennsylvania B402270547 730606 gDRADOCK 05000277 PDR 1

.