s JOSEPH M. FARLEY NUCLEAR PLANT UNIT 1 NARRATIVE

SUMMARY

OF OPERATIONS JANUARY, 1984 i

During the month of January, there was one (1) automatic shutdown which occurred on January 9, 1984.

The following safety-related maintenance was performed in the month of January:

1.

Performed miscellaneous maintenance on diesel generators.

2.

Replaced IB waste gas compressor.

3.

Repacked #4 river water pamp.

i 4.

Replaced vacuum pump on radiation monitor R-11.

5.

Replaced' cell #40 on 1A auxiliary building battery bank.

6.

Repaired control circuit on containment spray suction valve 8826B.

t 8402170127 840131 PDR ADOCM 05000348 R-PDR:

m (1

. - _ - - - _ _ _ _ - - - - - - -l DOCTETNO.

50-348 I

UNIT 2/7/8A pgg

\\

W

'. Hairston, III COMPLETED SY..

Tv? cpHONE (205) 899-5156 January, 1984 510NT11 DAY AVEMCE daily POWER LEVEL DAY' AVERAGE DAILY POWER LEVEi.

($1Wc Net)

(51We-Net) 811 805 g,

g7 2

13 801 807 2

19 808 4

g 806 5

21 Rng 809 6

536 n

7 777 23 807 801 801 g

4 784 J01 9

25' 10 0

26 804 O

804 II 77 0

806 12

3 13 288
9 808 776 08 14 30 15 804 810 3g 16 805 l

l

!? G U G O N S On 'his form::.list the sve.,ge daily umt power levelin MWe Net for e:ch 67 n the reporting munth. Gmpute to i

, the neare:t whole mepwat.

(9(77) i I

.1

o i

f i

i OPERATING DATA REPORT DOCKET NO 50-348 i

DATE 2/7/Rd COMPLETED BY W.G.Hairston, III TELEPHONE (?ns m og_s156 i

OPERATING STATUS f

Josaph M. Farley - Unit 1 Notes g, y,g, %

2. Reporting reded:

January. 1984

1) Cumulative data since 12/1/77, date of i
3. Licensed Thermal Power (MWt):

W7 commercial operation.

4. Namepiste Rating (Gross MWe):

860 829 i

5. Deng, Electrual Rating (Net MWe):

844.6

[

6. Maximum Dependable Capacity (Gross MWe):

803.6 l

7. Maximum Dependeble Capacity (Net Mbe):
8. If Changes Occur irt Capacity Rating: (Items Number 3 Through 7) Since.Last Report. 'iive Reasons:

w /a f

9. Power Level To Wluch Restricted,1f Any (Net MWe):

w/A l

10. Reasons For Restdctions.If Any:

N/A i

l This Month Yr to.Date Cumulative l

I II. Hours in Reporting Period 744 744 54.072 698.0 698.0 35,821.2

12. Number Of Hours Reactor Was Critical
13. Reactar Reserve Shutdown Hours 0.0 0.0 3,650.7 r

664.5 664.5 34,767.9 l

14. Hours Generator On.Line
15. Unit Reserve Shutdown Hours 0.0 0.0

. 0

16. Grom Thermal Energy Generated (htWH) 1,729,356 1,729,356 87,830,882 l
17. Grom Electrical Energy Generated (MWH) 548,662

' _548,662 27,891,672 l

18. N;t Electrical Energy Generated (MWH) 518,276 518,276 26,219,338 l
19. Unit Sersice Factor 89.3 89.3 64.3 l
20. Unit Availab3ity Factor 89.3 89.3 64.3 86.7 86.7 60.3
21. Unit Capacity Factor (Using MDC Net) 84.0 84.0 58.5 j
22. Unit Capacity Factor (Using DER Net)
23. Unit Forced Outage Rate 10.7 10.7 lu l
24. Shutdowns Scheduled Over Next 6 Months (Type.Date.and Duration of Eachi:

Refueling / maintenance outage 2/1C/84. approximate 1v 8 ve.h.

25. If Shut Down At End Of Report Period. Estimated Date of Startup.

N/A I

26. Uniti In Test Status (Prior to Commercial Operation):

Forecast Achieved

..Ni7i4 L CRl7iCALITY 8/6/77 8/9/77 8/20/77

~8/18/77 INITIAL ELECTRICITY COMMERCIAL OPERATION 12/1/77 12/1/77 i

l (o -

l I

UNIT SlHITDOhNS AND POWER REDUCTIONS DOCKET NO. 50-348 UNIT NAklE J.M. Farley-Unit 1 DATE 2/7/84 COhlPLETEI) BY W. G. Hairston, III REPORT hf0 Nill _ January,1984 TEl.LPilONE (205) 899-5156 I

=

a

.E E 3

jE'j g-]1, Lkensee E r, cause a cuiveceive No.

Date

(

il g E 5 a:

Event gy a

Auton in

$E 5 i j ig g Repori

  • Pievent Recurrence F

mt>

6 001 840106 F

0 h

4 NA ID TRB Reduced power to 30% to repair main turbine bearing oil leak.

002 840109 F

79.5 A

3 84-001-00 SL P

Rx trip due to 10-10 level in IB S/G following 1A SGFP trip.

I i

l 2

3 4

F: 1:osted Reason:

hiethod:

Exhibit G Insienctions S: Stheiluted A 1quipment Failure (Emplain)

I hianual for Picparation of Data 11 klaintenance ni Test 2 hla.uul Scram.

Entry Sheels for I.iienwe C RcIncling

3. Autonulx Scrans.

Esent Reposi(1.1 R) lite INtlREG.

D llegulatiny Hestrittion 4 Othes (limplaisi) 0161I l..Orcoator 1eaining & license T.mamination i

F-Administrative '

5 G Opreatienal 1.ssur (Enplain) thhibis I. S.une Sousic (9/77)

II Olhes (17uplain) i l

A ~

Malling Address Alabama Power Company 6rh Ncrth 18th Street Post Office Box 2641 Birmingham, Alabama 35291 Tolephone 205 783-6081 F. L Clayton, Jr.

Senior Vice President

)

Flintndge Building AlabamaPower 1

the southem electnc system February 10, 1984 Docket No. 50-348 Director, Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington,Q.C.

20555

Dear Sir:

RE: Joseph M. Farley Nuclear Plant Unit 1 Monthly Operating Data Report Attached are two (2) copies of the January,1984 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Unit 1, required by Section 6.9.1.10 of the Appendix A Technical Specifications. As requested by letter from Mr. John F. Stolz to Mr. Alan R. Barton, dated October 21, 1977, a

" Narrative Summary of Operating Experience" is included in the attached report.

If you have any questions, please advise.

Yours very truly, l

. L. Clayto, Jr.

FLCJr/KWM: sam Enclosures xc: Mr. Ted Cintula (1 copy)