Interim Deficiency Rept DER 83-60 Re Vitro Wiring in Main Steam & Feedwater Actuation Sys Not Meeting IEEE-384 Separation Criteria.Initially Reported on 830901.Final Rept Will Be Submitted by 840222
ML20086K252
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 01/04/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-28551-BSK, DER-83-60, NUDOCS 8401260370
Download: ML20086K252 (2)


Text

._.

7

_y,-

.y g

,g

.L E M NED SG Arizona Public Service Company

'PHOEMX, ARIZONA 85036

,,,, g g P.o. BOX 21666 *

@ jlI !C

,M 5'

1 January 4,1984 M ^'Z 'IT I -

ANPP-28551-BSK/KCP U. S; Nuclear Regulatory Commission Region V i

Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Tire Extension For Report - DER 83-60 l

A 50.55(e) Potentially Reportable Deficiency Relating To Wiring In Unit 2 Main Steam And Feedwater Actuation System By

~

Virro Does Not Meet IEEE-384 Separation Criteria.

File: 84-019-026; D.4.33.2

Reference:

(A) Telephone conversation between P. Narbut and R. Tucker on-September 1,1983 4

(B) ANPP-27911 dated. October 3,1983 (Interim Report)

(C) ANPP-28324 dated, November 30,1983 (Time Extension)

Dear Sir:

-The NRC was notified of a potentially reportable deficiency in i

Reference ~(A), an Interim Report was transmitted by Reference (B),

and a Time Extension was requested by Reference (C). At that time, it was estimated that a Final Report would be available by December 28, 1983.

Due to the-extensive investigation and evaluation required, it is now expected that ' this information will.be finalized by February 22, 1984, at which time a complete report will be submitted.

l There is no new information or change to the Interim Report at this-time.

Very truly y rs,

(-

M mA E.

E.- Van Brunt, Jr.

APS Vice President Nuclear Projects Management ANPP Project-Director j~

EEVB/KCP:db cc: See Page Two 8401260370 840104 "

I}

i ppR ADOCK 05000529.

PDRr S

g,)7

~"t..

.9:

\\

+

'Mr. T.-W. Bishop

DER. 83-60

-Page Two ace:

. Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory _ Commission Washington, D. C. 20555 T. G. Woods, Jr.

G. C. Andognini

'~

_ J. A. Roedel D. B. Fasnacht A. C.. Rogers B. S.' Kaplan W. E. Ide J. Vorees J. R. Bynum l

D. ' D. Green -

P..P. Klute l

A.

C.' Gehr W. J. Stubblefield W. G. Bingham

~

s R. L. Patterson'

- R. W. Welcher R. M. Grant D. R. Hawkinson

- L. E. Vorderbrueggen

- G. A. Fiorelli S. R. Frost J. ' Self l

D. Canady i

' Records Center

[

Institute of Nuclear Power Operations

[

1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339

~