Final Deficiency Rept DER 83-46 Re Manual Overtorquing of Borg-Warner Valve During Hydrostatic Testing,Resulting in Mounting Bolt Failure.Corrective Actions Enumerated.Also Reportable Under Part 21
ML20086K195
Person / Time
Site: Palo Verde  
Issue date: 01/09/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
REF-PT21-84 ANPP-28577-BSK, DER-83-46, NUDOCS 8401260341
Download: ML20086K195 (4)


Text

.

iEcav10 ii _'

Arizona Public Service Company P O. BOX 21666 + PHOENIX. ARIZONA 85036 1I3 j!N ! C P!. 1; I 7 January 9, 1984 ANPP-28577-BSK/TRB gr,' ], ;.;f U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Final Report - DER 83-46 l

A 50.55(e) Reportable Condition Relating to Borg Warner Valve Manually Over-Torqued During Hydro-Static Testing.

File: 84-019-026; D.4.33.2 Ref erence: A) Telephone Conversation between P. Narbut and R. Tucker on July 15, 1983 B) ANPP-27559, dated August 12, 1983 (Interim Repo t)

C)' ANPP-27910, dated September 28, 1983 (Time Extrasion)

D) ANPP-28482, dated December 21, 1983 (Time Extersion)

Dear Sir:

Attached is our final written report of the Reportable Deficiency under 10CFR50.55(e), referenced above.

Very truly ours.,

CL L L E. E. Van Brunt, Jr.

APS Vice President Nuclear Projects Management ANPP Project Director EEVB/TRB:ru Attachment cc: See Page Two I l 8401260341 840109 PDR ADOCK 05000528 l[ - ) }

S PDR

Mr. T. W. Bishop DER 83-46 Page Two cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

J. A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees J. R. Bynum D. D. Green P. P. Klute A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Pa tterson R. W. Welcher H. Foster D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli S. R. Frost J. Self D. Canady Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339

FINAL REPORT - DER 83-46 DEFICIENCY EVALUATION 50.55(e)

ARIZONA PUBLIC SERVICE COMPANY (APS)

PVNGS UNITS 1, 2, & 3 I.

Description of Deficiency While performing hydro-static testing at PVNGS Unit 2, motor operated valve (MOV) 2J-CHA-HV-524 was manually closed to the extent that the 5/16" mounting bolts, fastening the actuator to the valve yoke, failed.. Review of vendor documentation indicated that the valve maximum allowable rim pull is 40 lbs.

It has been determined that during testing the maximum 40 lb. pull requirement was not exceeded. The valve is supplied by Combustion Engineering (C-E) and maaufactured by Borg-Warner.

C-E's investigation indicated that this problem is applicable to Borg-Warner part Nos. 77610 and 83110. The corresponding PVNGS valve tag numbers are Units 1 and 2 CH-524 (2 inch) and Units 1 I

and 2 CH-255 (1 1/2 inch).

II.

Analysis of Safety Implications Valve CH-255 is installed as an Outside Containment isolation valve for the Reactor Coolant Pump (RCP) seal injection line. Valve CH-524 is installed as Outside Containment isolation valve for the

. charging pump line.

Both valves have safety-related functions as defined by C-E letter V-CE-19011.

Letter V-CE-19011 attributes the~ mounting bolt failure to inadequate bolt material selection and an insufficient number of mounting bolts required to adequately secure the motor operator to _ the valve yoke assembly and satisfy the 40 lb. rim pull requirement.

In addition Borg-Warner has indicated that damage to the valve also might have

(

occurred if'a locked rotor motor operation of the valve had l,

occurred. However, C-E's specification No. 00000-PE-707, Rev. 2

~

requires that no damage to the valve shall be sustained by this event. Therefore, Borg-Warner will provide redesigned valve stems l

and rims as required, to preclude damage to the pressure retaining l

parts due to manual or electric motor overtorquing events.

I Based on the above, this condition is evaluated as reportable under the requirements of 10CFR50.55(e) as a significant deviation from l

the design specifications, and if left uncorrected, this deficiency would represent a significant safety condition. The PVNGS project also evaluates this condition to be reportable under the requirements of 10CFR Part 21.

Deficiency Report 83-46 addresses j

the reporting requirements of 10CFR Part 21.21(b) (3), with the exception of sub-part (vi) which requires the number and location of other possible defective components, l

i l

l

Final Report DER 83-46 Page Two III. Corrective Action A.

C-E letter V-CE-20369, recommends as an interim solutio.3.that the subject valves be limited to less than 25 lbs. rim p'.tll, until the problem is fully corrected.

B.

C-E letter V-CE-19199 provides the Borg-Warner Field Rework Prodedure (Report No. 2023) for modification to the identified Unit 1 and 2 valves.. Bechtel will implement the following

~ modifications, before first fuel load, via Design Change Packages (DCP's) ISM-CH-163 and 2SM-CH-163 as follows:

Replace existing moun' ing bolts with ASTM A193, Grade B7.

c Modify valve yoke, by drilling two new holes, to accept 1/2 inch ASTM A193, Grade B7 bolts.

Install Borg-Warner stem and disc field kit.

C.

NCR PA-6267 will be dispositioned as per A and B above.

D.

C-E has stated that Unit 3 valves have not been delivered to PVNGS and that modifications will be performed by Borg-Warner prior to delivery.

E.

C-E will submit revised drawings, manuals and documentation related to the Borg-Warner valve modifications.

F.

A copy of this report will be sent to C-E for their review and disposition in accordance with - the requirements of 10CFR21.

References:

C-E letters V-CE-190ll dated 9/19/83 V-CE-19199 dated 10/26/83 V-CE-20257 dated 3/8/83 V-CE-20369 dated 6/24/83

--