March 26, 2020 Mr. Paul Garcia Quality Assurance Manager Framatome Fuel Facility 2101 Horn Rapids Road Richland, WA 99534
SUBJECT:
POSTPONEMENT OF PREVIOUSLY ANNOUNCED INSPECTION NO. 99902083/2020-201
Dear Mr. Garcia:
As discussed in a letter dated February 11, 2020, (Agencywide Document Access and Management System Accession No. ML20041E794), the Nuclear Regulatory Commission (NRC) planned to perform an inspection of Framatome Fuel Facility (Framatome) to review the implementation of Framatomes quality assurance program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B and 10 CFR Part 21. The letter discussed a preliminary schedule for the inspection. The NRC inspection team planned to arrive at your facility in Richland, Washington on Monday, March 30, 2020, and conduct the inspection through Friday, April 3, 2020. Due to the ongoing pandemic associated with the Corona virus, the NRC has decided to postpone the inspection at this time. The NRC will contact you within the next few weeks to reschedule the inspection.
Please contact Ms. Andrea Keim at 301-415-1671 or via electronic mail at Andrea.Keim@nrc.gov, if you have any questions or need assistance regarding this matter.
Sincerely, Kerri A. Kavanagh, Chief /RA/
Quality Assurance and Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation Docket No.: 99902083
ML20086J258 via email
- NRR-106 OFFICE NRR/DRO NRR/DRO*
NAME AKeim KKavanagh DATE 03/26/2020 03/26/2020