Interim Deficiency Rept DER 82-73 Re Itt Grinnel Improperly Secured Pipe Support Clamps.Initially Reported on 821124. Investigation in Progress.Next Rept Will Be Submitted by 840113
ML20086G502
Person / Time
Site: Palo Verde 
Issue date: 12/19/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-28460-BSK, DER-82-73, NUDOCS 8401120209
Download: ML20086G502 (2)


Text

_ ______

!!ECEmg

!! c Arizona Public Service Company P.o Box 21666 + PHOENIX ARIZONA 85036 December 19, 1983

'~

ANPP-28460-BSK/KCP gg, VVp U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention:.

Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs

Subject:

Time Extension for Report - DER 82-73 A 50.55(e) Potentially Reporttable Condition Relating To ITT Grinnel Pipe Support Clamps In Unit 2 MSSS Have Excess Cap, May Not Properly Secure Pipe.

File: 83-019-026; D.4.33.2

Reference:

(A) Telephone Conversation between P. Narbut and G. Duckworth on November 24, 1982 (B) ANPP-22589, dated December 23, 1982 (Interim Report)

(C) ANPP-23222, dated March 10, 1983 (Time Extension)

(D) ANPP-23428, dated April 5,1983 (Time Extension)

(E) ANPP-24002, dated June 8,1983 (Time Extension)

(F) ANPP-27536, dated August 8,19R3 (Interim Report, Rev.1)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Ref erence (B), and Time Extensions were requested by References (C), (D), and (E), and a revised Interim Report was submitted in Reference (F). At that time, it was estimated that a Final Report would be available by December 13, 1983.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by January 13, 1984, at which time a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours hld CLt L

~

E. E. Van Brunt, Jr.

8401120209 831219 APS Vice President, PDR ADOCK 05000529 Nuclear Projects Management S

PDR ANPP Project Director EEVBJr/KCP:ru cc: See Page 2 b

Mr. T. W. Bishop.

DER 82-73 Page 2

.cc:.

- Richard DeYoung, Director Office.of Inspection and Enforcement U. S. Nuclear Regulatory Commission

. Washington, D.-C.

20555 T. G. Woods, Jr.

'G.

C. Andognini J. A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees

.-T. R. Bynum -

D. D. Green /P. P. Klute A. C. Gehr W. J.'Stubblefield W. G. Bingham R..L.

Patterson

.R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiore111 S. R. Frost J. Self D. Canady Records Center Institute of Nuclear Power Operations 1100. Circle 75 Parkway - Suite 1500

- Atlanta, Georgia 30339 n

-,-