w..-
PIIILADELPIllA ELECTRIC COMPANY NUCLEAR GROUP llEADQUARTERS 955-65 CllESTERBROOK BLVD.
WAYNE, PA 19087-5691 (215) 640-6000 NUCI LAR ENGINEERINO & $0RVICES DEPARTMENT November 27, 1991 Docket Nos. 50-352 50-353 License Nos. NPF-39 NPF-85 U.S.
Nuclear Regulatory Commission Attn:
Document Control Desk Washington, DC 20555
Subject:
Limerick Generating Station, Units 1 and 2 Generic Letter 88-20, " Individual Plant Examinations for Severn Accir'ent Vulne~ abilities" Change to Intermediate Milestone Completion Date Gentlemen:
Our "05000352/LER-1988-021-01, :on 880601,main Control Room HVAC Sys Isolated Due to Channel D High Chlorine Isolation Signal.Caused by Rainwater Contacting Chlorine Analyzer Probe D.Special Event Procedure [[drawing" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Implemented|letter dated October 31, 1989]], provided our approach!
methodology, and schedule for completing the Individual Plant Examination (IPE) for Limerick Generating Station (LGS), Units 1 and 2.
This information was submitted in response to NRC Generic Letter 88-20, " Individual Plant Examinations for Severe Accident Vulnerabilities," and its Supplement 1.
By letter dated January 9, 1990, the NRC accepted our schedule for completing the IPE for LGS, Units 1 and 2.
Our "05000352/LER-1988-021-01, :on 880601,main Control Room HVAC Sys Isolated Due to Channel D High Chlorine Isolation Signal.Caused by Rainwater Contacting Chlorine Analyzer Probe D.Special Event Procedure [[drawing" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Implemented|October 31, 1989 letter]] specified completion of the intermediate milestone to investigate hardware and procedure chances by the entl of November, 1991.
The completion of this milestone is contingent upon establishing the risk profile and identifying insights from the IPE results that will ultima % ty form the basis of the submittal of the IPE results to the NRC.
For the reason explained below, the completian date for inveatigating hardware and procedure changes has been changed to January, 1992.
The IPE review process involving both internal as well as external expert reviews of the IPE methodology and results is in progress.
These reviews have identified changes to the models and results of the LGS Probabilistic Risk Assessment (PRA) to make them more realistic and consistent with current data sources and the PRA parformed as part of the IPE effort for our Peach Bottom Atomic Power Station (PBAPS), Unics 2 and 3.
These changes have shifted the distribution of the contributors to core camage frequency, and Od
-Osom m m POR ADOCK 05000352
{ \\Q p
FDR
~
5L'dS Units 1 and 2.
November 27, 1991
- ~
-Ge.neric Letter 88-20.
Page 2 therefore have changed the basis on which hardware and procedure change recommendations are made.
As a result, completion of the intermediate IPE milestone.to investigate hardware and procedure
-l l
changes is being deferred to the end of January, 1992.
This change 1
l will not impact the schedule for comp 1vtion and submittal of the LGS IPE to the NRC specified in our "05000352/LER-1988-021-01, :on 880601,main Control Room HVAC Sys Isolated Due to Channel D High Chlorine Isolation Signal.Caused by Rainwater Contacting Chlorine Analyzer Probe D.Special Event Procedure [[drawing" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Implemented|October 31, 1989 letter]].
If you have any questions or need additional information, please contact us.
l l
Very truly yours, fjfj 6 l[
L G. J.' Beck, Manager L
Licensing Section l.
.cc:
T. T. Martin, Administrator, Region I, USNRC T.
J. Kenny, USNRC Senior Resident Inspector, LGS l
l.
L l'
l l
. ~...
.,. _.. ~. _. - _.