ML20086G011

From kanterella
Jump to navigation Jump to search
Telecopy AO 75-57:on 750817,reactor Recirculation Sys Outboard Sample Isolation Valve AO-2-2-40 Failed to Close During Testing.Caused by Stuck Solenoid Valve.Solenoid Valve Disassembled,Cleaned & Repaired
ML20086G011
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 08/18/1975
From: Ullrich W
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20086G009 List:
References
AO-75-57, NUDOCS 8401090792
Download: ML20086G011 (1)


Text

. .

4 I

r PHILADELPHIA ELECTRIC CO!!PANY / ~'

P t a c h-Bo t .e "-

  • t+-- t e P aue "

A t n tion Delta Pennsylvania 1731k l l

August 18, 1975 1 Mr. Janea P. O'Reilly, Director l Office of Inspection and Enforcement 1AN {

Region 1 United States nuclear Regulatory Concission gg ,  ;

631 Park Avenue King of Prussia. Pennsylvania 19406 i

~

Subject:

Ahn rirr al Occurrence 2L: Hour N'o t i f i c a i. l o ri Confirning V. T. U11 rich's phone conversation with Mr. Jim Partlov, Region 1, United States Euclear Regulatory Cm.rd ssion.nn August 17. 29Y5

Reference:

Licence Nueber DPH-bh

, _ _ s.m t ut g _ ._ m r_ 1en y,. =r- n- - i- _ - - - - <m n - < r.? ; t _--- - - -

Report No.: 50-277-75-57 <-

Report Date: August 1C 1975 Occurrence Date: August 17, 1975 Facility: Peach Botton Atomic Power Station R.D. 1, Delta, Pennsylvania 1731h Identification of Occurrence: .

Reactor Recirculation Systen Outboard Sample Isolation Valve, AO-2-2-L@

failure to close during test. .

Conditione Prior to Occurrence: . .

Unit 2 reactor shut'down..

Description of Occurrence:

During the performance of ST 1.3, the PCIS Logic System Functional Testo

, valve AO-2-2-hD failed to close.

Designation of Apparent Cause of Occurrence:

Stuck solenoid valve.

- Analysis of Occurrence:

The cafety significance of this occurrence is minimal since the inboard isolation valve AO-2-2-35 was found to close satisfactorily.

Corrective Action:

The solenoid valve was disassembled, cleaned.and repaired. The valve was retested subsequent to repair. In the interin, the inboard isolati@

t valve AO-2-2-3d was caintained closed.

s -

failure Data:

j Previous failures of this type were reported as:

' AO-50-277-75-14 (Failure of AO-2-39 to fully close)

AO-50-278-74-23 (Pailure of AO-2-39 to fully close)

Very truly yours,. .

W / $ C t"l- d W. T. Ullrich, Superintendent Peach Botton Atocic Power Station' MS4 - svtumsvernreetermwamch.o-.r -,- _ --.-- -- - -, -, mara 8401090792 750027