Interim Deficiency Rept DER 83-54 Re Washers & Plug Found Inside Steam Generator.Initially Reported on 830802.Bechtel & C-E Determining Reportability Disposition & Technical Justification for Corrective Actions.Final Rept Due 831013
ML20085H558
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 08/22/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-27603-BSK, DER-83-54, NUDOCS 8309120030
Download: ML20085H558 (3)


Text

..

go-9N Ag f

EI)

.~,

CJJg %f Arizona Public Service Conipany P O. Box 21666. PHOENIX. ARIZONA 85036 q f,,

August 22, 1983

'8Cic,4 ANPP-27603-BSK/RQT kA U. S. Nuclear Regulatory Commiss' ion Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. D. M. Sternberg, Chief Reactor Projects Branch 1

Subject:

Interim Report - DER 83-54 A 50.55(e) Potentially Reportable Deficiency Relating to Washers Found In Unit 1 Steam Generator #1 And #2 File:

83-019-026; D.4.3 3.2

Reference:

Telephone Conversation between P. Narbut and R. Tucker en August 2, 1983

Dear Sir:

The NRC was notified of a potentially reportable deficiency in the referenced telephone conversation. At that time, it was estimated that a determination of reportability would be made within thirty (30) days.

Due to the extensive investigation and evaluation required, an Interim Report is attached. It is now expected that this information will be finalized by October 13, 1983, at which time a complete report will be submitted.

Very truly yours, b

Ow w

(

E. E. Van Brunt, Jr.

APS Vice President, Nuclear Projects Management ANPP Project Director EEVBJr./RQT:sn Attachment cc:

See Attached Page Two 8309120030 830822 PDR ADOCK 05000528 1

.ff47

~

U. S. Nuclear Regulatory Commission Page Two cc: Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

G. C. Andognini J. A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees J. R. Bynum P. P. Klute/D. D. Green A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli S. R. Frost J.-Self Records Canter Institute of Nuclear Power Operations 1100. Circle 75 Parkway - Suite 1500 Atlanta, Georgia 30339

INTERIM REPORT - DER 83-54 POTENTIAL REPORTABLE DEFICIENCY ARIZONA PUBLIC SERVICE COMPANY (APS)

PVNGS UNIT 1 I.

Potential Problem During initial inspection of Steam Generator #2, eleven (11) bevel washers and one plug were found inside the Steam Generator on the side next to the Reactor Vessel. One (1) washer was found in Steam Generator fl.

II.

Approach To and. Status _Of Proposed Resq14 tion Bechtel engineering is corresponding with C-E to provide reportability disposition and technical justification for corrective action.

III. P_r_qiected. Completion Of Cor,rective, Action and. Submittal of.The final Report Evaluation of this condition and submittal of the Final Report is

. forecast to be completed by October 13, 1983.