Forwards Monthly Operating Rept for Sept 1991 for Jm Farley Nuclear Plant,Unit 2 & Rev to Aug 1991 Unit 2 Operating Data Rept Which Incorporates Correction to Cummulative Unit Capacity Factor
ML20085E416
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 10/14/1991
From: Dennis Morey
ALABAMA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20085E418 List:
References
NUDOCS 9110180219
Download: ML20085E416 (2)


Text

F...

Aw.na swe, con nai4 40 inwmen renNo hd wer list Orfap 0;u t"p, (WfruhyWti, Autinnia 3* P01 Triephane N!i Ot n !Sid

w. n. iwrm.a. m h

bi.nna yg n Pecadent ome,a < ve.n.

AlilbilnlilPOWef October 14, 1991 Docket No. 50-364 U. S. Nuclear Regulatory Conunisslon ATIN: Document Control Desk Washington, D. C.

20555 Joseph M. farley Nuclear plant Unit 2

_.thulhlLOR0HlinLURLROR0rl_.

Gentlemen:

Attached is the September 1991 Monthly Operating Report for Joseph M.

f arley Nuclear Plant Unit 2, as required by Section 6.9.1.10 of the Technical Specifications.

Also included is a revision to the August 1991 Unit 2 Operating Data Report which incorporates a correction to the Cummulative Unit c.apacity f actor (using MDC not).

If you have any questions, please advise, Respectfully submitted, f 4,/ /rblI_h 1

W. G. Itairston, 111 AEJ:cdb3014 Attachments cc: Mr. S. D. fbneter Mr. S. T. lloffman Mr.

G'. f. Maxwell

^

a 9110100?!O 910930 PDR

(\\ DOCK 05000364 k

R PDR

JOSCPM N. FARLEY NUCLEAR PLANT UNIT 2 NARRATIVE

SUMMARY

OF OPERATIONS September 1991 on September 7 at 2300, ramp-down was initiated to approximately 60 percent to perform governor valve testing and for repairs to an electro-hydraulic leak on 2B steam generator feedwater pump. Tne unit returned to 100 percent power on September 8 at 1045.

There were no unit shutdowns during the month.

The following major safety-related maintenance was performed during the month:

1.

Miscellanee: Sporrective and preventive maintenance was performed on the diesel generators.

2.

2E service water pump motor was replaced and returned to service on 9-28-91.