Clarifies 840327 Submittal Re Justification for Delay of Isolation Condenser Vent Installation Until Next Refueling Outage (Cycle 11).Existing Flow Path Would Be Utilized When Necessary Until New Vent Line to Torus Installed
ML20084L727
Person / Time
Site: Oyster Creek
Issue date: 05/08/1984
From: Fiedler P
GENERAL PUBLIC UTILITIES CORP.
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
NUDOCS 8405150005
Download: ML20084L727 (2)


Text

e

(-

GPU Nuclear Corporation NUCIMr 100 lnterpace Parkway Parsippany, New Jersey 07054 201 263-6500 TELEX 136-482 Writer's Direct Dial Number:

May 8, 1984 Mr. Dennis M. Crutchfield, Chief Operating Reactors Branch #5 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Crutchfield:

Subject:

Oyster Creek Nuclear Generating Statica Docket No. 50-219 Isolation Condenser Vent Installation In your letter of January 17, 1984, it was requested that GPUNC provide additional information to justify delaying the installation of vents on the isolation condensers until the next refueling outage (Cycle 11).

GPUNC provided a response to this request on March 27, 1984.

The purpose of this letter is to clarify some of the information contained in the March 27, 1984 submittal. This clarification was requested by Mr. Mark Wigdor of your staff and consists of the following information.

First, it is the position of GPUNC that, during the next cperating cycle, the existing isolation condenser vent flow path would be utilized whenever deemed necessary and until such time as the new vent line to the torus is installed and operational (Cycle ll).

Second, in response to a question regarding the Probabilistic Risk Analysis for Oyster Creek, the total frequency of core damage caused by approximately 9 x 10 -5,er year. g seismic, fires, floods, etc.) is internal events (that is excludin p

And third, estimates obtained from our Project Engineering staff show that the installation of the new Isolation Condenser vent line to the torus would extend the present outage an additional six months.

840515000b 9

PDR ADOCK 0 pop

)

GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation

.. If you have further questions regarding this information, please call Mr.

M. W. Laggart at (201) 299-2341.

Very truly yours, Vice President and Director Oyster Creek 1r/0237e cc: Administrator Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pa.

19406 NRC Resident Inspector Oyster Creek Nuclear Generating Station Forked River, N.J.