Ro:On 720812,during Verification of Mod 201-2-72,timer 2-1705-23 in Offgas Sys Discovered Inoperable.Caused by Loose Drive Gear for Timer Motor Armature.New Timer Installed
ML20084J458
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 08/17/1972
From: Palmer F
COMMONWEALTH EDISON CO.
To: Oleary J
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML20084J462 List:
References
FAP-72-158, NUDOCS 8305120638
Download: ML20084J458 (2)


Text

~

309-6.54 2241

~~ A So-y,4 y

Commonwealth Edison Company Q U A D.C I TI E S NUCLEAR POWER ST A TION u.....s, POST CHICE BOX 216

  • CORDOVA, ILUNot$ 61242

-(

ew n' O[Q',.$

August 17, 1972 S-

/.i :

q g?r i'I0 :

,e h.:h.0:.

'FAP-72-158 v.y w

\\,

t' 4

%/phht k'

Mr. J.F. O' Leary Director, Directorate of Licensing U.S. Atomic Energy Commission Washington, D. C.

20545

~

Dear Mr. O' Leary:

Ref:

Quad-Cities Nuclear Powei Station Unit 2 - DPR-30 Appendix A Sections 1.0.A.2, 3.2.D.1 and 6.6.A.3 The purpose of this letter is to inform you of the details regarding the failure of timer 2-1705-23 in the off-gas systen at Ouad-Cities Station Unit 2.

This incident occurred on August 12, 1972.

?

Descriotion of Incident The incident occurred during a Unit 2 outage with the reactor subcritical.

While trying to verify modification #201-2-72 7 f3 it was discovered that timer 2-1705-23 in the off-gas system

.i would not operate.

The timer is designed to be energized on high off-gas radiation to automatically close off-gas isola-tion valve AO-2-5406 and condensate isolation valve AO-2-5408 i

p after a fifteen minute _ time delay.

W gF) ln

$0hg o,{n%yg5

~

\\*

g PDR

~ -

q COPY SENT REGION m.

4 a

^

O

-.O 6

O'N V

.v.

'.J Mr. J. F. O ' Le ary August 17, 1972 3

~

Investigation and Corrective Action Investigation indicated that one of the drive gears for

-l the motor armature of timer 2-1705-23 had come loose causing the malfunction.

A new timer was installed and e

functionally tested to operate properly.

Timer 2-1705-23 was declared operable at 2 P.M., August 12, 1972.

p Very truly yours, COMMONWEALTH EDISON COMPANY Quad-Cities Nuclear Power Station f>W F.A. Palmer Superintendent FAP/dct a%e 4