Suppl to 840327 Final Deficiency Rept 413-414/81-11.Unit 2 Mods & Repairs Will Be Completed by 840615.Unit 1 Completion Date Correct
ML20084G609
Person / Time
Site: Catawba  
Issue date: 04/11/1984
From: Tucker H
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
413-414-81-11, NUDOCS 8405070292
Download: ML20084G609 (1)


Text

-.

DUKn Powna Gom*ANY P.O. I,0X 3)leM)

CHAH1.OTTE. N.C. 2452 42 "i"J."E" all$'ir"CEu April 11, 1984 Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Conunission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Re: Catawba Nuclear Station Units 1 and 2 Docket Nos. 50-413 and 50-414

Dear Mr. O'Reilly:

My letter of March 27,1984 transmitted the final report on Significant Deficiency No. 413-414/81-11, which stated that all modifications and repairs have been completed. This is correct for Unit 1 only. Unit 2 repairs will be completed by June 15, 1984.

Very truly yours, o.k D.Ttk8>c th.c Hal B. Tucker LTP/php cc: Director INPO Records Center Office of Inspection & Enforcement Suite 1500 l

U. S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C. 20555 Atlanta, Georgia 30339 NRC Resident Inspector Mr. Robert Guild, Esq.

Catawba Nuclear Station Attorney-at-Law P. O. Box 12097 Palmetto Alliance Charleston, South Carolina 29412 21351 Devine Street Columbia, South Carolina 29205 t