Interim Significant Deficiency Rept 413-414/83-17.Completion of Unit 1 Extended to 840427 Due to Rework,Rehydro Testing & Cleaning of Q-1As,F-13As & R-6as for Items Discussed in 840329 Rept.Completion Date for Unit 2 Achievable
ML20084G482
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 04/13/1984
From: Tucker H
DUKE POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
413-414-83-17, NUDOCS 8405070241
Download: ML20084G482 (1)


Text

DUKE POWElt GoxPm P.O. HOX 33180 CitAHLOTTE, N.C. 28242 HAL II. TUCKER TELEPitONE (704) 373-4531 vus emeneouw,

" " ~ " ~ ~ ~ "

April 13,1984 Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30303 Re: Catawba Nuclear Station Units 1 and 2 Docket Nos. 50-413 and 50-414

Dear Mr. O'Reilly:

In the Supplement to Significant Deficiency Report No. 413-414/83-17, dated March 29, 1984, it was stated that the completion date for Unit I would be April 15, 1984.

Rework, rehydro testing, and clearing of Q-1A's, F-13A's, and R-6a's for the additional items discussed in the supplement make it necessary to extend the completion date to April 27, 1984. The completion date for Unit 2 is still achievable.

Very truly yours, M S Tech ~b-C Hal B. Tucker LTP/php cc:

Director INP0 Records Center Office of Inspection & Enforcement Suite 1500

- U. S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C. 20555 Atlanta, Georgia 30339 i

NRC Resident Inspector Mr. Robert Guild, Esq.

Catawba Nuclear Station Attorney-at-Law P. O. Box 12097 Palmetto Alliance Charleston, South Carolina 29412 21351 Devine Street Columbia, South Carolina 29205 e405070241 840413 PDR ADOCK 05000413 S

PDR l

rem.