Clarifies 790710 Response to IE Bulletin 79-02 Pipe Support Baseplate.Designs Using Concrete Anchor Bolts. Preload Not Required for Anchor Bolts Using Design Criteria for Facility
ML20084B265
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 04/02/1984
From: Mangan C
NIAGARA MOHAWK POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
(NMP2L-0022), (NMP2L-22), IEB-79-02, IEB-79-2, NUDOCS 8404260136
Download: ML20084B265 (1)


Text

M Y NIAGARA R UMOHAWK NIAGARA MOHAWK POWER CORPORATION /300 ER;E BOULEVARD WEST SYRACUSE. N Y.13202/ TELEPHONE (315) 474-1511 April 2, 1984 (NMP2L 0022)

Mr. R. W. Starostecki, Director U.S. Nuclear Regulatory Commission Region I Division of Project and Resident Programs 631 Park Avenue King of Prussia, PA 19406 Re: Nine Mile Point Unit 2 Docket No. 50-410

Dear Mr. Starostecki:

The following provides a clarification to our July 10, 1979 letter concerning I.E.Bulletin 79-02, " Pipe Support Baseplate Designs Using Concrete Expansion Anchor Bolts."

Response 4(a) should be revised to read as follows:

a.

All anchors are set to a prescribed preload as determined in the onsite test program.

It is recognized that over a period of time anchors will lose varying amounts of preload.

However, the design does not require any remaining preload to assure a safety factor of 4.

In recent tests at Hanford Engineering Development Labs regarding NUREG/CR2999 HEDL-MISC-7246, a final report by United States Nuclear Regulatory Commission entitled " Anchor Bolt Study - Data Survey and Dynamic Testing" concluded, "The ultimate strength, under low cycle dynamic loading, of the anchors tested was not affected by initial preload level." Preload is not a requirement for the anchor bolts using the design criteria for Nine Mile Point Unit 2.

Very truly yours, 84o4260136 840402 QAyWLpq f ADEK 05000 C. V. Mangaiv Vice. President