Revised Monthly Operating Rept for Mar 1995 for Vogtle Electric Generating Plant Unit 1
ML20083C187
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/31/1995
From: Hooper G
GEORGIA POWER CO.
To:
Shared Package
ML20083C154 List:
References
NUDOCS 9505150190
Download: ML20083C187 (2)


Text

,

i j

l i

ENCLOSURE 4 VOGTLE ELECTRIC GENERATING PLANT - UNIT 1 MONTHLY OPERATING REPORT FOR MARCH 1995 l

TABLE OF CONTENTS OPERATING DATA REPORT Page VI-2 i

t 9505150190 950508 PDR ADOCK 05000424 R

PDR

OPERATING DATA REPORT DOCKET NO. 50-424 DATE:

MAY 1,1995 COMPLETED BY: G. L. HOOPER j

TELEPHONE:

(706) 826-4104 i

OPERATING STATUS

1. UNIT NAME:

VEGP UNIT 1

2. REPORT PERIOD:

MARCH 1995

3. LICENSED THERMAL POWER (MWt):

3565

4. NAMEPLATE RATING (GROSS MWe):

1215-

5. DESIGN ELECTRICAL RATING (NET MWe):

1169

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):

1216

7. MAXIMUM DEPENDABLE CAPACITY (NET MWe):

1162

8. IF CHANGES OCCUR IN CAPACITY RATINGS t

(ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):

NO RESTRICTIONS

10. REASONS FOR RESTRICTION, IF ANY:

NA THIS MONTH YR. TO DATE CUMULATIVE

.. HOURS IN REPORTING PERIOD:

744 2160 68665

12. NUMBER OF HOURS REACTOR WAS CRITICAL:

744.0 2160.0 59924.6 l

13. REACTOR RESERVE SHUTDOWN HOURS:

0 0

0

14. HOURS GENERATOR ON-LINE:

744.0 2087.6 58808.4

15. UNIT RESERVE SHUTDOWN HOURS:

0 0

0

16. GROSS THERMAL ENERGY GENERATED (MWH):

2650182 7431180 198224481

17. GROSS ELEC. ENERGY GENERATED (MWH):

911252 2543170 66769857 I

18. NET ELEC. ENERGY GENERATED (MWH):

871782

  • 2428640
  • 63487087 *
19. REACTOR SERVICE FACTOR 100.0 %

100.0 %

87.3 %

20. REACTOR AVAILABILITY FACTOR 100.0 %

100.0 %

87.3 %

21. UNIT SERVICE FACTOR:

100.0 %

96.6 %

85.6%

i

22. UNIT AVAILABILITY FACTOR:

100.0 % '

96.6 %

85.6 %

23. UNIT CAPACITY FACTOR (USING MDC NET):

100.8 %

96.8 %

83.4 %

24. UNIT CAPACITY FACTOR (USING DER NET):

100.2 %

96.2 %

82.8 %

25. UNIT FORCED OUTAGE RATE:

0.00 %

0.00%

4.72 %

26. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE. AND DURATION OF EACH):

NONE

27. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

NA

  • REVISED V1-2