Safety Evaluation Supporting Amend 177 to License DPR-49
ML20082V343
Person / Time
Site: Duane Arnold 
Issue date: 09/13/1991
From:
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20082V329 List:
References
NUDOCS 9109230215
Download: ML20082V343 (2)


Text

_ - _ _ - _ _ _ _ _ _ _ _ _ _

g ** *' 4 9'9,,

UNIT E D sT ATES 8'

'n NUCLE AR REGULATORY COMMISSION I

WWHNOTON, O C. 20tM 5

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO.177 TO FAClllTY OPERATING LICENSE NO. DPR-49 10WA ELECTRIC LIGHT AND POWER COMPANY CENTRAL IOWA POWER C00P MATIVE

~ TORN BELT POWER c003 RAT 1vr DUANE ARNOLD ENERGY CENTER DOCKET NO. 50-331

1.0 INTRODUCTION

By letter dated March 8, 1991, Iowa Electric Light and Power Company (IELP) requested changes to the Duane Arnold Energy Center (DAEC) Operating License (OL) to extend effectiveness of the DAEC Plan for Integrated Scheduling of Plant Modifications for DAEC from May 3, 1991 (the expiration date specified in Amendment 161), to May 3,1996.

This change to subparagraph 2 of paragraph 2.C(6) of the OL will allow IELP to continue the use of its Integrated Plan.

This request is being submitted with no changes to the Integrated Plan as asproved by the NRC under Amendments 91, 125, 148, and 161 with the exception that the new extension will be for a 5-year period instead of 2 years.

2.0 EVALUATION The Integrated Plan is purely an administrative scheduling tool which facili-tates IELP's effective management of implementation of plant modifications which have been required or proposed by the NRC as'well as other measures to enhance plant safety and reliability which have been identified by lELP.

The plan integrates planned work at DAEC over a nominal 5-year period to ensure that individual tasks are effectively scheduled and coordinated while reflecting that fiscal and manpower resources are finite and that a limit on the on-site manpower is necessary.

Therefore, continuation of the use of the Integrated Plan has no effect on the safe operation of the plant, its systems and/or its eouipment. Conse-quently, the staff has concluded that extending the expiration date of the Plan for Integrated Scheduling from May 3, 1991, to May 3, 1996 will not affect the safe operation of the DAEC.

Based on the above discussion, the staff concludes that this proposed amendment is acceptable.

9109230215 910913 PDR ADDCK 05000331 P

PDR

1 2

3.0 STATE CONSULTATION

in accordance with the Commission's regulations, the Iowa State official was notified of the proposed issuance of the amendment. The State official 1

had no comments.

4.0 fNVIRONMENTAL CONSIDERATIONS This amendment relates to changes in recordkeeping, reporting, or administrative procedures or requirements. Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(10)(56 FR 375PS).

Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.

5.0 CONCLUSION

The staff has concluded, based on the considerations discussed above, that: (1) be endangered by operation in the proposed manner, (2) y of the public will not there is reasonable assurance that the health and safet such activities will be conducted in compliance with the Conmission's regulations, and (3) the issuance of the amendnent will not be inimical to the common defense and security or to the health and safety of the public, principal Contributor:

C. Y. Shiraki Date: September 13. 1991 l