PACIFIC GAS AND ELECTR,IC C O M PANY bbW3 l
77 BEALE STREET
- SAN F RANCISCO,. CALIFORNI A 94106. (415) 781 4211. TWX 910-372 6587 J.O.SCHUYLE!R nucLean ese st=tearson December 9,1983 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Comission Washington, D. C. 20555 Mr. John B. Martin, Regional Administrator U. S. Nuclear Regulatory Commission, Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596-5368 Re: Docket No. 50-275, OL-DPR-76 Diablo Canyon Unit No.1
Subject:
Design Verification Program Fifty-First Semimonthly Status Report
Dear Sirs:
In accoroance with Commission Order CLI-81-30, enclosed is Pacific Gas and Electric Company's (PGandE) Fifty-First Semimonthly Status Report dated December 9,1983, for the Diablo Canyon Design Verification Program.
This report summarizes the progress of technical work from November 22, 1983 through December 9,1983.
Since the Diablo Canyon Design Verification Program is now complete, as stated in PGandE's submittal dated December 1,1983, this will be the final issuance of the Semimonthly Status Report.
Sincerely,
J. O.
chuyler Enclosure cc:
Dr. W. E. Cooper G. W. Knighton H. E. Schierling Service List