ML20082P678

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Rdc 68(83) Re Brown Boveri Class IE Low Voltage Switchgear.Site Engineering Evaluating Equivalent Site Approved Welding Procedure for Utilization on Cubicle EFZC05.Final Rept by 840430
ML20082P678
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 11/29/1983
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8312090133
Download: ML20082P678 (1)


Text

'

)

18  : u; li t v . ,

a

e r t~IilL P.O. BOX 5000 - CLEVELAND, OHIO 44101 - TELEPHONE (216) 622-9800 - lLLUMINATING BLDG. - 55 PUBLIOSOUARE Serving The Best Location in the Nation MURRAY R. EDELMAN VICE PRESIDENT NUCLE A R Mr. James G. Keppler Regional Administrator, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE: Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Deficiency in the Class 1E Low Voltage Switchgear RDC [68(83)]

Dear Mr. Keppler:

As stated in our interim report to you dated April 27, 1983, a welding repair is to be conducted to correct a deficiency in one cubicle, EF2C05, supplied to Perry Nuclear Power Plant by the Brown Boveri Electric Ccmpany (BBE). Our letter to you identified that this welding repair would be completed by November 30, 1983.

While BBE has submitted the required instruction and a qualified welding procedure to PNPP, the site electrical contractor does not have in pince a procedure which covers BBE welding requirements. Site engineering therefore is presently evaluating an equivalent site approved welding procedure for utilization on cubicle EF2C05. Due to this delay, we now plan to suimit the final report on this subject by April 30, 1984.

Please call me if there are additional questions.

Sincerely, 8312090a33 831129 W-PDR ADOCK 050004eO urray R. Edelman S PDH Vice President Nuclear Group MRE:pab cc: Mr. M. L. Gildner NRC Site Office Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 U.S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D.C. 20555 Records Center, SEE-IN Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 g