ML20082M444

From kanterella
Jump to navigation Jump to search
Interim Deficiency Rept Re Vulkene Supreme Cable Terminations.Initially Reported on 830620.Final Rept Expected by 840128
ML20082M444
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 11/23/1983
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, KMLNRC-83-151, NUDOCS 8312060143
Download: ML20082M444 (1)


Text

KANSAS GAS AND ELECTRIC COMPANY YW ELECTRIC COMPANY GLENN L MOESTER vect passiotu an.fn.am November 23, 1983 IA { f ' (r j j'C 1

Mr. J. E. Gagliardo, Acting Chief N

Reactor Projects Branch 2 U.S. Nuclear Regulatory Commission Region IV Arlington, Texas 76011 KMLNRC 83-151 Re:

Docket No. STN 50-482 Re f:

1)

Interim Report KMLNRC 83-095 dated 7/20/83 from GLKoester, KG&E, to WCSeidle, NRC 2)

Interim Report KMLNRC 83-125 dated 9/28/83 from GLKoester, KG&E, to WCSeidle, NRC Subj:

Interim 10CFR50.55(e) Report - Vulkene Supreme Cable Terminations

Dear Mr. Gagliardo:

This letter provides an interim report on the subject potential 10CFR50.55(e) which was initially reported by Kansas Gas and Electric Company (KG&E) on June 20, 1983. Additional information was subsequently provided in Refer-ences 1 and 2.

i After reviewing the available information, KG&E has concluded that the l

identified concern is reportable pursuant to 10CFR50.55(e) and is in the l

process of developing corrective actions to resolve this matter. A final report (or interim report if necessary) will be submitted to you on or befcre January 28, 1984. In the interim, please direct any questions con-cerning this subject to me or Mr. Otto Maynard of my staff.

1 Very truly yours, j/