Forwards Semimonthly Status Rept 50 for Design Verification Program,Per Commission Order CLI-81-30.Rept Summarizes Progress of Technical Work for 831108-21
ML20082G683
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 11/23/1983
From: Schuyler J
PACIFIC GAS & ELECTRIC CO.
To: Harold Denton, Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V), Office of Nuclear Reactor Regulation
Shared Package
ML20082G685 List:
References
CLI-81-30, NUDOCS 8311300298
Download: ML20082G683 (1)


Text

,

e-.. ,

PACIFIC GAS AND ELECTR,IC C O M PANY MON #3 l 77 BEALE STREET . SAN FRANCISCO, CALIFORNIA 94106 * (415) 781 4211

  • TWX 910-372 6587

.J.O.SCHUYLER vect retstorni NGCLE AR POmEN GEME.ATION November 23, 1983 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Mr. John B. Martin, Regional Administrator U. S. Nuclear Regulatory Commission, Region Y 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596-5368 Re: Docket No. 50-275, OL-DPR-76 Diablo Canyon Unit No.1

Subject:

Design Verification Program Fiftieth Semimonthly Status Report

Dear Sirs:

In accordance with Commission Order CLI-81-30, enclosed is Pacific Gas and Electric Company's (PGandE) Fiftieth Semimonthly Status Report dated November 23, 1983, for the Diablo Canyon design verification program. This report summarizes the progress of technical work from November 8,1983 through November 21, 1983.

Sincerely, J

Enclosure cc: Dr. W. E. Cooper G. W. Knighton H. E. Schierling Service List

~