Interim Deficiency Rept DER 83-37 Re Missed Factory Operations on Steam Generator 2.Initially Reported on 830628.Due to Extensive Evaluation,Next Rept Will Not Be Submitted Until 831216
ML20082F630
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 11/02/1983
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, ANPP-28160-BSK, DER-83-37, NUDOCS 8311290173
Download: ML20082F630 (2)


Text

r e

HEGy0 y {VGo Arizona Public Service Company /yyy

~

P 0, BOX 21666 e P IA. ARIZONA 85036

/ %A n'0'! 2 3 m 7. g & g.

November 2, 1983 8/C//p*.

A'kO428160-BSK/RQT E U.- S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. T W. Bishop, Director, Division of Resident, Reactor Projects and Engineering Programs

Subject:

Time Extension for Report - DER 83-37 A 50.55(e) Potentially Reportable Condition Relating To Missed Factory Operations On Unit 3 Steam Generator #2 File: 83-019-026; D.4.33.2 Ref ere nce: (A) Telephone Conversation between A. D'Angelo and

!- R. Tucker on June 28, 1983 (B) ANPP-27368, dated June 28,1983 (Interim Report)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference ( A), and an Interim Report was transmitted by Reference (B).

. At that time, it was estimated that a Final Report would be available by November 1, 1983.

. Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by December 16, 1983, at which time a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours k

., a -- -

( - . CLLL A LL l E. E. Van Brunt, Jr.

APS Vice President, Nuclear Projects Management 4

Al@P Project Director EEVBJr/RQT:ru cc: See Page 2 n

8311290173 831102 [ '_ ,

PDR ADOCK 05000530 S PDR A

j' v

gg IN,,

~ ?*

o Mr. T. W. Bishop DER 83-37 Page 2 cc: Richard DeYoung Director

. Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 T. G. Woods, Jr.

G. C.~ Andognini J.~ A. Roedel D. B. Fasnacht A. C. Rogers B. S. Kaplan W. E. Ide J. Vorees J. R. Bynum O D. D. Green /P.'P. Klute A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher

.R. M. Grant D. R. Hawkinson L. E. Vorderbrueggen G. A. Fiorelli S. R. Frost J. Self D. Canady

. Record s Cent >2r Institute of Nuclear Power Operations l

11100 Circle 75 Parkway - Suite 1500 Atlanta, Georgia 30339 l

i l

I i

_