, e e BOSTON EOlsON COMPANY BOD BOYLSTON STREET BOSTON, MASSACHUSETTS 02199 WILLIAM D. HARRINGTO N asseeon vesa pnessesser seu s taan October 26, 1983 BECo 83-267 Mr. Domenic B. Vassallo, Chief Operating Reactors Branch #2 Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 License No. DPR-35 Docket No. 50-293

Subject:

Commitment Dates Associated with Supplement 1 to NUREG-0737

References:

(A) Boston Edison letter dated April 15, 1983 (B) Boston Edison letter dated July 1, 1983 (C) Telephone conversation on September 30, 1983 between Mr. V.

Rooney (NRC) and Mr. P.M. Kahler (Boston Edison)

Dear Sir:

This responds to the request of Reference (C) that Boston Edison restate the commitment dates contained in Reference (A) and clarified in Reference (B).

I.C.1 Upgrade Emergency Operation Procedures (E0P's)

Generating Package to be submitted to NRC: January 1,1984.

Implementation: November 28, 1984.

I.D.1 Control Room Design Review Submittal of program plan: October 15, 1983 (Please note that this has been submitted).

Submit a summary report with a proposed implementation date: September 23, 1984 I.D.2 Safety Parameter Display System Completion of conceptual design and submittal of our Safety Analysis: November 15, 1984.

i Submittal of final implementation commitments: December 20, 1984.

8311010396 831026 hDRADDCK 05000293 PDR

. a CO3 TON EDCON COMPANY Mr. Domenic B. Vassallo, Chief Page 2 Regulatory Guide 1.97, Rev. 2 Submittal of a report on how Pilgrim meets Regulatory Guide 1.97, and how we plan to meet it where it does not: November 1, 1984.

III.A.1.2 Upgrade Emergency Support Facilities Submittal of our plan to make the new Technical Support Center (TSC) and Opera-tional Support Center (OSC) fully functional: November 2, 1983.

The Emergency Operations Facility is not included in this ef fort. Reference (A) stated that our present facilities are adequate. Though we have received indica-tions that NRC does not concur with our position, we have received no documented indication or reason for the position being unacceptable.

Such information is essential for us to assess the available options and develop an implementation plan should one be necessary. Based on this, we shall address the E0F as a separate issue, and any commitments and plans stemming from it will be submitted six months from our receipt of the NRC's documented position.

We believe this response satisfies your reauest in Reference (C). If you wish further information concerning it, please contact us.

Very truly yours, l WN PMK/ mat l

Commonwealth of Massachusetts)

County of Suffolk )

Then personally appeared before me W.D. Harrington, who, being duly sworn, did state that he is Senior Vice President - Nuclear of Boston Edison Company, the applicant herein, and that he is duly authorized to execute and file the submittal contained herein in the name and on behalf of Boston Edison Company and that the statements in said submittal are true to the best of his knowledge and belief.