Forwards Svc Water Sys Operational Performance Insp Self- Assessment Plan
ML20081C114
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 03/10/1995
From: Broughton T
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20081C118 List:
References
C311-95-2106, NUDOCS 9503170125
Download: ML20081C114 (2)


Text

..

( ,

A GPU Nuclear Corporation

- Nuclear an:nte Middletown, Pennsylvania 17057-0480 (717)944-7621 Writer's Direct Dial Number:

(717) 948-8005 March 10,1995 C311-95-2106 U. S. Nuclear Regulatory Commission Att: Document Control Desk Washington, DC 20555 Gentlemen:

Subject:

Three Mile Island Nuclear Station, Unit 1 (TMI-1)

Operating License No. DPR-50 Docket No. 50-289 '

Service Water System Operational Performance Inspection (SWSOPI) Self-Assessment Plan GPU Nuclear letter dated January 31, 1995 (C311-95-2039) proposed a SWSOPI self-assessment as an alternative to the full scope NRC inspection described in the NRC Temporary Instruction 2515/118, Revision 1, " Service Water System Operational Performance Inspection."

Enclosed for NRC review is the proposed THI-1 Self-Assessment Plan. The plan addresses scope, schedule, and the multi discipline team to be utilized in the assessment. GPU Nuclear requests NRC staff acceptance of this self-assessment as an alternative to the staff conducting a team inspection of this area.

This request is being made in accordance with the guidance of NRC Inspection Procedure 40501, " Licensee Self-Assessments Related to Area-of-Emphasis Inspections." We are planning to make a formal presentation to Region I staff to present the various elements of the attached plan. NRC concurrence of our ,

self-assessment plan is requested by March 31, 1995 to support start of the inspection by April 10, 1995.

1 Our self-assessment will fully meet the objectives and requirements specified in NRC Temporary Instruction 2515/118, Revision 1. The self-assessment project has an overall team leader, a co-team leader, an assessment team, and a response team. Individuals are assigned to each of the teams for the duration of the inspection. The response team members will be GPU Nuclear and '

Gilbert Commonwealth employees. The self-assessment team is composed of GPU Nuclear employees, .an employee from another utility with experience in service water systems, and consultants from industry. The self-assessment team members have been salected consistent with the guidance provided in TI 2515/118 and IP 4050L and consultant team members have been selected based on ,

their experience in conbicting similar inspections.

I 9503170125 950310 M.

PDR ADOCK 05000239

' V l g PDR l GPU Nwlear Corporabon is a subsidiary of General Pubhc Utsties Corporat!on

r-0311'-9'5-2106 Page 2 The self-assessment activities are scheduled to begin April 10, 1995 and continue for approximately six (6) weeks. A formal entrance meeting is scheduled for April 24, 1995. The Final Assessment Report is scheduled for issuance in mid-July 1995. GPU Nuclear will provide the self-assessment results and corrective actions to the NRC at that time.

If any additional information is needed, please contact David Distel, Senior Licensing Engineer at (201) 316-7955.

Sincerely,

$6 -lJ u T. G. B hton, Vice President and Director, TMI Enclosure DJD/plp cc: Administrator, Region I THI Senior Resident Inspector TMI NRC Senior Project Manager E. M. Kelly - Division of Reactor Safety, Region I